Question

As part of a major plant renovation project, the industrial engineering department has been asked to...

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

   

Task Duration
(minutes)
Immediate
Predecessor
a 0.2 -
b 0.4 a
c 0.2 b
d 0.4 -
e 1.2 d
f 1.2 c
g 1.0 e, f

d. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

Answer:

   

Work stations Following Tasks
I A, B, D, C
II E
III F
IV G

e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 2 decimal places. Omit the "%" sign in your response.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

- s 2. Вона г. Сум fімі 4 - - - F i langet Duration 10.2 0.4 0. 2 1 B-E-G 1.9 1.21 2 1.6 Tale Thuo 1.2 0.4 0.4 min = 20

Add a comment
Know the answer?
Add Answer to:
As part of a major plant renovation project, the industrial engineering department has been asked to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • e As part of a major plant renovation project, the industrial engineering department has been asked...

    e As part of a major plant renovation project, the industrial engineering department has been asked to balance an assembly operation. Assume full 8 hours are available per day. Precedence relationships and tasks times are shown below. If daily demand is 285 units of output, there needs to be workstations to meet the demand. The answer is an integer Task Time (minutes) Cycle time (c) Theoretical minimum number of stations (TM) = Idle time = nc - Et Efficiency (%)...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • A producer of inkjet printers is planning to add a new line of printers, and you...

    A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...

  • You have been asked to balance a flow shop assembly operation to achieve an output rate...

    You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...

  • 4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you...

    4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you have been asked to bal- ance the assembly line, given the following task times and precedence relationships. Assume that cycle time is 1.3 minutes per unit. Task Duration (minutes) 0.2 Immediate Follower 0.4 0.3 1.3 oooo s T 0.1 0.8 0.3 1.2 a. Do each of the following: i. Draw the precedence network. ii. Assign the tasks to workstations using the heuristic rule "Assign...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

    For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...

  • IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight...

    IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight hour work day. The tasks, times, and predecessor activities involved in the production process are given below. Task Time (minutes) Predecessor(s) A 2 - B 2 A C 8 - D 6 C E 3 B F 10 D, E G 4 F H 3 G a) Determine the cycle time. b) How many work stations are required to produce the forty units of...

  • 1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls...

    1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls per 40-hour workweek. The process of servicing calls can be broken down into the six stations listed above. The precedence and time requirements for each element are as follows in the table below. The manager wants a new operational analyst to draw and label a precedence diagram for the service process. Finally, the manager needs to balance the line, calculate the efficiency of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT