2. Show all the steps for the question to be worth any marks.
a.
b)
Required cycle time = Available time/desired output = (8*60)/320 = 1.5 minutes
c)
Theoretical minimum number of workstations = Sum of task times/cycle time = 5.9/1.5 = 3.933333333 = 4 (Rounded to next whole number)
d)
Activity | Positional weight |
A | 2.9 |
B | 4.2 |
C | 3.5 |
D | 3.4 |
E | 2.7 |
F | 2 |
G | 2.2 |
H | 1.6 |
I | 1.1 |
e)
Workstation | Feasible task | Assigned task | task time | Idle time remaining |
I | A,B,C | B | 0.7 | 0.8 |
A,C,D | C | 0.8 | 0 | |
II | A,D,E | D | 0.4 | 1.1 |
A,E | A | 0.9 | 0.2 | |
III | E,F | E | 0.5 | 1 |
F,G | G | 0.6 | 0.4 | |
F | F | 0.4 | 0 | |
IV | H | H | 0.5 | 1 |
V | I | I | 1.1 | 0.4 |
f)
Efficiency = Sum of task times/(no of workstations*cycle time) = (5.9/(5*1.5))*100 = 78.66666667%
2. Show all the steps for the question to be worth any marks. The following table...
3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...
I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...
Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...
4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you have been asked to bal- ance the assembly line, given the following task times and precedence relationships. Assume that cycle time is 1.3 minutes per unit. Task Duration (minutes) 0.2 Immediate Follower 0.4 0.3 1.3 oooo s T 0.1 0.8 0.3 1.2 a. Do each of the following: i. Draw the precedence network. ii. Assign the tasks to workstations using the heuristic rule "Assign...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...
Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best line balance their production process. There are 12 steps to the production process, and they are presented below, along with their predecessors and how long it takes to complete each task. Assume all times are in minutes. This facility operates for 7 hours per day. Task C D E F G H I J K L A B Nil A B B B B...
The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks
Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...