4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you have been asked to bal- ance the ass
Task Duration (minutes) 0.2 Immediate Follower 0.4 0.3 1.3 oooo s T 0.1 0.8 0.3 1.2 a. Do each of the following: i. Draw the
0 0
Add a comment Improve this question Transcribed image text
Answer #0

(i)

php7tQ5bI.png

(ii)

Station Remaining time Eligibles
(# followers)
Was fit Assigned time Time remains Idle time Tie-breaker
I 1.3 a(4), c(3), e(3) a 0.2 1.1
1.1 c(3), e(3), b(3) b 0.4 0.7 b
0.7 c(3), e(3) c 0.3 0.4 c
0.4 e(3), d(2) e 0.1 0.3
0.3 d(2), f(2) - - 0.3 0.3
II 1.3 d(2), f(2) d 1.3 0.0 d
0.0 f(2) - - 0.0 0.0
III 1.3 f(2) f 0.8 0.5
0.5 g(1) g 0.3 0.2
0.2 h(0) - - 0.2 0.2
IV 1.3 h(0) h 1.2 0.1 0.1

So, the assignment is as follows:

Station-I: a, b, c, e
Station-II: d
Station-III: f, g
Station-IV: h

(iii)

Percentage idle time = Total idle time per cycle / (No. of stations * cycle time) = (0.3+0+0.2+0.1) / (4*1.3) = 11.54%

(iv)

The actual cycle time is also 1.3 minutes (Station-II being the bottleneck).

So, actual output in 420 minutes = 420/1.3 = 323 units per day

Add a comment
Know the answer?
Add Answer to:
4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • A producer of inkjet printers is planning to add a new line of printers, and you...

    A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....

    EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...

  • As part of a major plant renovation project, the industrial engineering department has been asked to...

    As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:     Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...

  • SHOW EQUATIONS uestion 10 0/ Te (min) 10 For the diagram above, available time per shift...

    SHOW EQUATIONS uestion 10 0/ Te (min) 10 For the diagram above, available time per shift is 480 minutes and 40 units are required at the end of each shift. Use the heuristic rule by assigning the task with the most followers. Break any ties with longest time first. (all time in minutes) (6 marks) 480/40-12 Hide Feedback This was not a balance line uestion 10 0/ Te (min) 10 For the diagram above, available time per shift is 480...

  • I need help with the total idle time per cycle question, please include steps with explanations...

    I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...

  • Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per...

    Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT