Question

EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length of the arrows has no meaning.) Determine workstation cycle time. Here we have to convert to seconds because our task times are in seconds. 2. Production time per day 60 sec. X 420 min. Output per day 500 wagons 25.200 504 500 Determine the theoretical minimum number of workstations required (the actual num- ber may be greater): T 195 seconds , C-50.4 seconds 3.87 = 4 (rounded up) 4. Select assignment rules. In general, the strategy is to use a rule assigning tasks that either have many followers or are of long duration because they effectively limit the balance achievable. In this case, we use the following as our primary rule: a. Prioritize tasks in order of the largest number of following tasks. NUMBER OF FOLLOWING TASKS TASK Bor D C or E F G, H. or l Our secondary rule, to be invoked where ties exist from our primary rule, is b. Prioritize tasks in order of longest task time (shown in Exhibit 8.10). Note that D should be assigned before B, and E assigned before C due to this tiebreaking rule.
media%2F23f%2F23f020a5-6294-4577-b3f7-26
media%2Fca7%2Fca7c5879-964a-4735-b157-f3
media%2F3ca%2F3caa5a81-ee43-4893-aeb3-f8
0 0
Add a comment Improve this question Transcribed image text
Answer #1

b) Cycle Time= 60*420/500 = 50.4 sec

c) Minimum number of workstations= sum of total task times / cycle time

                        = 195/50.4 = 3.872 = 4 workstations

Task Table

Task

Task time

Followers

Followers #

Precedence

A

45

B,C,F,G,J,K

6

-

B

11

C,F,G,J,K

5

A

C

9

F,G,J,K

4

B

D

50

E,H,I,J,K

5

-

E

15

H,I,J,K

4

D

F

12

J,K

2

C

G

12

J,K

2

C

H

12

J,K

2

E

I

12

J,K

2

E

J

8

K

1

F,G,H,I

K

9

-

0

J

The total station time is nothing but the cycle time. So, total station time of each station is 50.4 secs.

In order of longest task time and then on the largest no of following tasks, tasks:

D>A>E>H>I>B>C>F>G>J>K

               Workstation 1:

                        First task =D

                        Time left= 50.4-50 = 0.4 secs

                       

So, workstation 1: D

Workstation 2:

                        First task =A

                        Time left= 50.4-45 = 5.4 sec

                       

So, workstation 2: A

Workstation 3:

                        First task=E

                        Time left= 50.4-15= 35.4 sec

                        Second task=H

                        Time left=35.4-12 = 23.4 sec

                        Third task=I

                        Time left=23.4-12 = 11.4 sec

                        Fourth task=B

                        Time left=11.4-11 = 0.4 sec

So, workstation 3: E->H->I->B

Workstation 4:

                        First task= C

                        Time left=50.4 – 9= 41.4 secs

                        Second task=F

                        Time left=41.4-12 = 29.4 sec

                        Third task=G

                        Time left=29.4-12 = 17.4 sec

                        Fourth task=J

                        Time left=17.4-8 = 9.4 sec

                        FIFTH task=K

                        Time left=9.4-9 = 0.4 sec

So, workstation 4: C->F->G->J->K

Work Station

Tasks

Workstation time

Idle Time

1

D

50

0.4

2

A

45

5.4

3

E->H->I->B

50

0.4

4

C->F->G->J->K

50

0.4

e) Total idle time = 0.4+5.4+0.4+0.4 = 6.6 sec

f) Efficiency with 4 workstations = (sum of all tasks) / (no of workstations *   Cycle time)

        = (195)/ (4*50.4) = 0.967 or 96.7 %

Add a comment
Know the answer?
Add Answer to:
EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed...

    This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed to operate 9.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times: PERFORMANCE PRECEDING TASK PERFORMANCE TIME (SECONDS) 25 30 15 10 40 20 PRECEDING TASK TASKS TIME (SECONDS) TASK 56 40 38 15 39 20 h,i j, k b. What is the workstation cycle time? Hint: draw the diagram first. tion...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal...

    Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Immediate Predecessor A B с D E Time (sec) 12 14 8 5 18 A A B,C D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20.57 seconds (round your response to two decimal places)....

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...

  • Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per...

    Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

  • An assembly line is to operate eight hours per day with a desired output of 240...

    An assembly line is to operate eight hours per day with a desired output of 240 units per day. The following precedence diagram contains information on this product’s task times and precedence relationships. What is the efficiency of your line balance, assuming it is running at the cycle time from part (a)? Determine the theoretical minimum number of workstations required (the actual number may be greater). 60 60

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT