Question

An assembly line is to operate eight hours per day with a desired output of 240 units per day. The following precedence diagram contains information on this product’s task times and precedence relationships.

What is the efficiency of your line balance, assuming it is running at the cycle time from part (a)?

Determine the theoretical minimum number of workstations required (the actual number may be greater).

60 60

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CYCLE TIME = OPERATING TIME / DESIRED OUTPUT

TOTAL OPERATING TIME = 8 * 60 * 60 = 28800

CYCLE TIME = 28800 / 240 = 120

THEORETICAL NUMBER OF WORKSTATIONS REQUIRED = SIGMA(TASK TIMES) / CYCLE TIME

N = (60 + 80 + 20 + 50 + 90 + 30 + 30 + 60) / 120 = 4

ASSIGNED USING PRECEDENCE RELATIONSHIP

WORKSTATION

ASSIGN TASK

TASK TIME

TIME REMAINING

IDLE TIME

1

A

60

60

D

50

10

10

2

B

80

40

C

20

20

20

3

E

90

30

F

30

0

0

4

G

30

90

H

60

30

30

TOTAL IDLE TIME = 60

EFFICIENCY = (1 - (SIGMA(IDLE TIME) / (NUMBER OF WORKSTATIONS * CYCLE TIME))) * 100

EFFICIENCY = (1 - (60 / (4 * 120))) * 100 = 87.5

Add a comment
Know the answer?
Add Answer to:
An assembly line is to operate eight hours per day with a desired output of 240...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An assembly line is to operate eight hours per day with a desired output of 160...

    An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....

    EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...

  • em 9.14 Question Help 3 per Sue Hains Appliances wants to establish an assembly line to...

    em 9.14 Question Help 3 per Sue Hains Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcom Popper. The goal is to produce five poppers per hour The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: estions: 3 Task tion 1 (0/1) А Performance Time Task Must Follow (mins Task Usted Below 10 12 А B 11 B,C 7 С 5 DE B D E F a)...

  • 4.22 The table below lists the work elements in minutes to be performed on assembly line...

    4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...

  • This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed...

    This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed to operate 9.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times: PERFORMANCE PRECEDING TASK PERFORMANCE TIME (SECONDS) 25 30 15 10 40 20 PRECEDING TASK TASKS TIME (SECONDS) TASK 56 40 38 15 39 20 h,i j, k b. What is the workstation cycle time? Hint: draw the diagram first. tion...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • 3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair...

    3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...

  • e As part of a major plant renovation project, the industrial engineering department has been asked...

    e As part of a major plant renovation project, the industrial engineering department has been asked to balance an assembly operation. Assume full 8 hours are available per day. Precedence relationships and tasks times are shown below. If daily demand is 285 units of output, there needs to be workstations to meet the demand. The answer is an integer Task Time (minutes) Cycle time (c) Theoretical minimum number of stations (TM) = Idle time = nc - Et Efficiency (%)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT