Theoretical minimum number of workstations
= Total duration of all tasks/ cycle time of operation
= 49/10 = 4.9 ( 5 rounded to nearest whole number )
THEORETICAL MINIMUM NUMBER OF WORKSTATIONS = 5
Workstation |
Tasks |
Total duration |
Idle time = Cycle time – total duration |
1 |
A |
4 |
10 – 4 = 6 |
2 |
B |
7 |
10 – 7 = 3 |
3 |
C |
6 |
10 – 6 = 4 |
4 |
D |
5 |
10 – 5 = 5 |
5 |
E |
6 |
10 – 6 = 4 |
6 |
F |
7 |
10 – 7 = 3 |
7 |
G |
8 |
10 – 8 = 2 |
8 |
H |
6 |
10 – 6 = 4 |
Therefore, total idle time in 8 hour shift i.e. for 48 chairs = 31 x 48 = 1488 minutes
= Total duration of all tasks/ ( actual number of workstations x cycle time) x 100
= 49/ ( 8 x 10 ) x 100
= 49/80 x 100
= 61.25%
3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair...
... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: TASK PERFORMANCE TIME (min) TASK MUST FOLLOW TASK LISTED BELOW A,B F, G a) Draw a precedence diagram of this operation. b) What is...
... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available dur- ing the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Must Follow Task Listed Below Performance Time Task (min) A4 B 7 C 6 AB E F,G a) Draw a precedence...
Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480480 minutes available during the day, and the average daily demand has been 5050 chairs. There are eight tasks: Task Performance Time(mins) Task Must Follow Task Listed Below A 44 minus− B 77 minus− C 77 A, B D 66 C E 55 D...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...
The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...
Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...
CAN YOU PLEASE HELP ME?The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:Questions;1) Draw a precedence diagram of this operation.2) In Question 1, given the demand, what is the cycle time for this operation? Write the formula, and show your calculations.3) For Question 1, what is the theoretical minimum number of workstations? Write the formula, and show your calculations.4) For, Question 1, assign tasks to workstations. 5) For Question 1,...
1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls per 40-hour workweek. The process of servicing calls can be broken down into the six stations listed above. The precedence and time requirements for each element are as follows in the table below. The manager wants a new operational analyst to draw and label a precedence diagram for the service process. Finally, the manager needs to balance the line, calculate the efficiency of the...
Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...