Question

... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The Executive Secretary is a chair that ha
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a)

4 min 7 min 6 min 5 min H 6 min 6 min B 7 min 8 min

b) Cycle time = (Production time per day) / (Output per day)

Cycle time = 480/50 = 9.6 minutes

c) Theoretical minimum number of workstations = (Sum of total task times) / Cycle time

49 min's / 9.6 min's

5.104 = 5 (rounded)

d, e, f

Stations Task Task time (minutes) No of following tasks Remaining un assigned time Feasible remaining tasks
1 A 4 7 5.6 None
2 B 7 6 2.6 None
3 C 6 5 3.6 None
4 D 5 4 4.6 None
5 E 6 3 3.6 None
6 G 7 1 2.6 None
7 F 8 1 1.6 None
8 H 6 0 3.6 None
Total IDLE time 27.8

g)

Efficiency of assembly line = (Sum of all task times) / (Actual no of workstations)x(Cycle time)

= (49) / (8)x(9.6)

= 0.638 OR 63.8 %

Add a comment
Know the answer?
Add Answer to:
... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a...

    ... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: TASK PERFORMANCE TIME (min) TASK MUST FOLLOW TASK LISTED BELOW A,B F, G a) Draw a precedence diagram of this operation. b) What is...

  • 3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair...

    3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...

  • Illinois​ Furniture, Inc., produces all types of office furniture. The​ "Executive Secretary" is a chair that...

    Illinois​ Furniture, Inc., produces all types of office furniture. The​ "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for​ $130. There are 480480 minutes available during the​ day, and the average daily demand has been 5050 chairs. There are eight​ tasks:                                                                                   Task Performance Time​(mins) Task Must Follow Task Listed Below A 44 minus− B 77 minus− C 77 ​A, B D 66 C E 55 D...

  • As part of a major plant renovation project, the industrial engineering department has been asked to...

    As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:     Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...

  • e As part of a major plant renovation project, the industrial engineering department has been asked...

    e As part of a major plant renovation project, the industrial engineering department has been asked to balance an assembly operation. Assume full 8 hours are available per day. Precedence relationships and tasks times are shown below. If daily demand is 285 units of output, there needs to be workstations to meet the demand. The answer is an integer Task Time (minutes) Cycle time (c) Theoretical minimum number of stations (TM) = Idle time = nc - Et Efficiency (%)...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • A producer of inkjet printers is planning to add a new line of printers, and you...

    A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight...

    IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight hour work day. The tasks, times, and predecessor activities involved in the production process are given below. Task Time (minutes) Predecessor(s) A 2 - B 2 A C 8 - D 6 C E 3 B F 10 D, E G 4 F H 3 G a) Determine the cycle time. b) How many work stations are required to produce the forty units of...

  • Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for...

    Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid filed compartments to provide more stability and better protection against knee, foot, and back injuries Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 62. The information for the tasks is as follows Task Performance Time (mins) Predecessors <UO a-b) The correct precedence...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT