... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The Executive Secretary” is a chair that has been

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Draw a precedence diagram: A 4min. 7 min. E 6min. 6min. 6min 7min. 8min. The precedence diagram was constructed using the

b) Calculate the cycle time: Cycle time is total time of the process from the beginning to the end. It is calculated by divid

Calculate the theoretical minimum number of workstations: It is calculated by dividing the total task time given with the cyc

Assign the tasks to workstations: Workstation Termi b le Assige Idle time 10 A A (4) 6 10 IB BO CCO D D45) 10 E EO 10 F F(8)

Initial task should be chosen. The remaining task is the next two task of the chosen task. The task, which has the maximum ta

Calculate the idle time per 8-hours shift: Workstations Chosen task Idle time 1 A, C 0 2 BL 3 3 E 4 4 F 3 5 G 2 6 H 4 7 D 5 T

e) Calculate the idle time per cycle: It is given that the average demand is 50 chairs, which means 50 cycles. Idle time per

Efficiency g) Calculate the efficiency of the assembly line: It is calculated by dividing the sum of task time with the value

Add a comment
Know the answer?
Add Answer to:
... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is...

    ... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available dur- ing the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Must Follow Task Listed Below Performance Time Task (min) A4 B 7 C 6 AB E F,G a) Draw a precedence...

  • 3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair...

    3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...

  • Illinois​ Furniture, Inc., produces all types of office furniture. The​ "Executive Secretary" is a chair that...

    Illinois​ Furniture, Inc., produces all types of office furniture. The​ "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for​ $130. There are 480480 minutes available during the​ day, and the average daily demand has been 5050 chairs. There are eight​ tasks:                                                                                   Task Performance Time​(mins) Task Must Follow Task Listed Below A 44 minus− B 77 minus− C 77 ​A, B D 66 C E 55 D...

  • I need help with the total idle time per cycle question, please include steps with explanations...

    I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...

  • e As part of a major plant renovation project, the industrial engineering department has been asked...

    e As part of a major plant renovation project, the industrial engineering department has been asked to balance an assembly operation. Assume full 8 hours are available per day. Precedence relationships and tasks times are shown below. If daily demand is 285 units of output, there needs to be workstations to meet the demand. The answer is an integer Task Time (minutes) Cycle time (c) Theoretical minimum number of stations (TM) = Idle time = nc - Et Efficiency (%)...

  • The Action Toy Company has decided to manufacture a new toy tractor, the production of which...

    The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,800 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS A 20 None B 30 A C 15 A D 15 A E 10 B,C F 30 D,E A) Draw a precedence diagram B) What is the cycle time? C) What is the theoretical minimum number of workstations? D) Assign tasks to workstations E)...

  • As part of a major plant renovation project, the industrial engineering department has been asked to...

    As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:     Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • Hello, I need to see the solution, how they got these numbers? Will appreciate help. The...

    Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT