Question

The Action Toy Company has decided to manufacture a new toy tractor, the production of which...

The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,800 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS

A 20 None

B 30 A

C 15 A

D 15 A

E 10 B,C

F 30 D,E

A) Draw a precedence diagram

B) What is the cycle time?

C) What is the theoretical minimum number of workstations?

D) Assign tasks to workstations

E) How much total idle time is present in each cycle?

1 0
Add a comment Improve this question Transcribed image text
Answer #1

A

B.cycle time = number of hours / number of units to be made

= 40x60 /4800 = 0.5 minutes = 30 seconds

C Theoritical minimum number of workstations = task time /cycle time = 120 /30 =4

However, praactically, the process would need 5 workstations.

D Assignment by highest number of followers

WS activities Time Idle time
1 A 20 10
2 B 30 0
3 C,D 30 0
4 E 10 20
5 F 30 0

Idle time per cycle = 30/5 = 6 seconds

Add a comment
Know the answer?
Add Answer to:
The Action Toy Company has decided to manufacture a new toy tractor, the production of which...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Layout Strategies Homework The Action Toy Company has decided to manufacture a new train set, the...

    Layout Strategies Homework The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps describe in the table below. The demand for the train is 4,800 units per 40 hour workweek. PLEASE ANSWER ALL QUESTIONS ONE BY ONE. Task Performance Time (second) Predecessors 20 А 15 15 DE 30 120 a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this operation?...

  • A toy company has decided to manufacture a new toy tractor, the production of which is...

    A toy company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 3800 units per 40-hour workweek: Performance Time (Seconds) 20 30 15 as Predecessor None 10 B, C 30 D, E What is the maximum cycle time that will ensure that the demand is met? (That is, what is a threshold on the cycle time, which is in seconds, that will ensure that demand is...

  • A toy company has decided to manufacture a new toy tractor, the production of which is...

    A toy company has decided to manufacture a new toy tractor, the production of which is made up of six steps. The demand for the tractor is 4800 units per 40-hour workweek: Question 2 Incorrect 0.00 points out of 5.00 P Flag question Performance Time (Seconds) 20 10 25 as Predecessor None 10 B, C 15 D, E For the 3 workstation configuration in which Station 1 is assigned tasks A and B; Station 2 is assigned tasks C and...

  • I need help with the total idle time per cycle question, please include steps with explanations...

    I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...

  • Hello, I need to see the solution, how they got these numbers? Will appreciate help. The...

    Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...

  • Operations Management Question

    CAN YOU PLEASE HELP ME?The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:Questions;1) Draw a precedence diagram of this operation.2) In Question 1, given the demand, what is the cycle time for this operation? Write the formula, and show your calculations.3) For Question 1, what is the theoretical minimum number of workstations? Write the formula, and show your calculations.4) For, Question 1, assign tasks to workstations. 5)  For Question 1,...

  • a) The cycle time for the production of a PDA = ____ seconds. b) The theoretical...

    a) The cycle time for the production of a PDA = ____ seconds. b) The theoretical minimum number of workstations that Rosenburg can achieve in this assembly line = ____. c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: ??? d) Were you able to assign all the tasks to the theoretical minimum number of workstations? Yes or No. Stanford Rosenberg Computing wants to...

  • Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal...

    Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Immediate Predecessor A B с D E Time (sec) 12 14 8 5 18 A A B,C D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20.57 seconds (round your response to two decimal places)....

  • Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per...

    Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...

  • ... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is...

    ... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available dur- ing the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Must Follow Task Listed Below Performance Time Task (min) A4 B 7 C 6 AB E F,G a) Draw a precedence...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT