Question

A toy company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 3800 units per 40-hour workweek: Performance Time (Seconds) 20 30 15 as Predecessor None 10 B, C 30 D, E What is the maximum cycle time that will ensure that the demand is met? (That is, what is a threshold on the cycle time, which is in seconds, that will ensure that demand is met?) Specify only the amount. e.g. 15. Answer: 6 The correct answer is: 37

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Available time per week (in seconds) = 40 hours * 3600 seconds per hour = 144000 seconds

Demand rate = 3800 units per week

Maximum cycle time to ensure the demand is met = Available time / Demand rate = 144000/3800

= 37.89 ~ 37 seconds (fraction part is removed as per question)

ANSWER: 37

Add a comment
Know the answer?
Add Answer to:
A toy company has decided to manufacture a new toy tractor, the production of which is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Action Toy Company has decided to manufacture a new toy tractor, the production of which...

    The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,800 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS A 20 None B 30 A C 15 A D 15 A E 10 B,C F 30 D,E A) Draw a precedence diagram B) What is the cycle time? C) What is the theoretical minimum number of workstations? D) Assign tasks to workstations E)...

  • A toy company has decided to manufacture a new toy tractor, the production of which is...

    A toy company has decided to manufacture a new toy tractor, the production of which is made up of six steps. The demand for the tractor is 4800 units per 40-hour workweek: Question 2 Incorrect 0.00 points out of 5.00 P Flag question Performance Time (Seconds) 20 10 25 as Predecessor None 10 B, C 15 D, E For the 3 workstation configuration in which Station 1 is assigned tasks A and B; Station 2 is assigned tasks C and...

  • Layout Strategies Homework The Action Toy Company has decided to manufacture a new train set, the...

    Layout Strategies Homework The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps describe in the table below. The demand for the train is 4,800 units per 40 hour workweek. PLEASE ANSWER ALL QUESTIONS ONE BY ONE. Task Performance Time (second) Predecessors 20 А 15 15 DE 30 120 a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this operation?...

  • I need help with the total idle time per cycle question, please include steps with explanations...

    I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...

  • Operations Management Question

    CAN YOU PLEASE HELP ME?The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:Questions;1) Draw a precedence diagram of this operation.2) In Question 1, given the demand, what is the cycle time for this operation? Write the formula, and show your calculations.3) For Question 1, what is the theoretical minimum number of workstations? Write the formula, and show your calculations.4) For, Question 1, assign tasks to workstations. 5)  For Question 1,...

  • Hello, I need to see the solution, how they got these numbers? Will appreciate help. The...

    Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...

  • A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed...

    A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed below Immediate Activity Description Estimated completion time (days) 90 15 Predecessors Prototype design Purchase of materials Manufacture of prototype Revision of design Initial production run Staff training Staff input on prototype Sales training Preproduction advertising campaign Post production advertising campaign 20 21 25 14 28 30 C,F D,I Management has also provided you with...

  • Cost benefit analysis for the Long Engineering Company        The Long Engineering Company (LEC) has decided...

    Cost benefit analysis for the Long Engineering Company        The Long Engineering Company (LEC) has decided to install a network system to help their technical support engineers (five of them who earn an average of $100,000 each per year) to deliver better customer service including: mail out sales and other literature, answer phone calls for technical assistance and log and forward repair requests using an alpha-numeric paging system that will be part of the new network system. Currently all company...

  • Introduction: A manufacturing company that possesses many complexities can be highly challenged when maintaining production goals...

    Introduction: A manufacturing company that possesses many complexities can be highly challenged when maintaining production goals and standards in conjunction with a major organizational change. Garment manufacturing is a complex industry for many reasons. The product line is a complex array of styles, seasons, varying life cycles and multidimensional sizing. Many sewn product firms are viewing TQM as the appropriate strategy to meet the double demand of competition and quality; however, many companies are finding sustaining their TQM adoption decision...

  • 1. Kinetics is the study of forces acting on a system. True False 2. Kinematics is...

    1. Kinetics is the study of forces acting on a system. True False 2. Kinematics is the study of motion without regard to its causes (forces). True False 3. The similarity between the Macrocycle Flowchart, the Training Pyramid and the Goals for Performance pyramid can be best described as an athlete should have a structured foundation and not proceed too early. True False 4. When should static stretching be performed? Minutes before event performance Hours prior to event or the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT