CYCLE TIME = OPERATING TIME / DESIRED OUTPUT
TOTAL OPERATING TIME = 8 * 60 = 480
CYCLE TIME = 480 / 285 = 1
THEORETICAL NUMBER OF WORKSTATIONS REQUIRED = SIGMA(TASK TIMES)
/ CYCLE TIME
N = (0.2 + 0.7 + 0.5 + 0.4 + 0.9 + 0.9 + 1) / 1 = 5
e As part of a major plant renovation project, the industrial engineering department has been asked...
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...
... 9.12 South Carolina Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available dur- ing the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Must Follow Task Listed Below Performance Time Task (min) A4 B 7 C 6 AB E F,G a) Draw a precedence...
... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: TASK PERFORMANCE TIME (min) TASK MUST FOLLOW TASK LISTED BELOW A,B F, G a) Draw a precedence diagram of this operation. b) What is...
3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...
You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...
A final assembly plant for Dictatape, a popular dictation company, produces the DT, a hand-held dictation unit. There are 400 minutes available in the final assembly plant for the DT, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table. Answer parts a through e. Afinal assembly plant for Dictatape, a popular dictation company, produces the DT, a hand-held dictation unit. There are 400 minutes...
CAN YOU PLEASE HELP ME?The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:Questions;1) Draw a precedence diagram of this operation.2) In Question 1, given the demand, what is the cycle time for this operation? Write the formula, and show your calculations.3) For Question 1, what is the theoretical minimum number of workstations? Write the formula, and show your calculations.4) For, Question 1, assign tasks to workstations. 5) For Question 1,...
I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...
a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in ? b) What is the operating efficiency of the assembly line, using your answer to (a)? c) What is the theoretical minimum number of workstations? d) What is the idle time per boat produced? IOIIGWufk. Cny Score: 0 of 1 pt Problem 9.18 Assembly Line Balancing 10 of 11 (6 complete) HW Score: 54.55%, 6 of 11 Question Holp The final assembly...
Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...