Question

You have been asked to balance a flow shop assembly operation to achieve an output rate...

You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below:

Task Predecessor Time (minutes)
A -- 2
B A 4
C 7
D A, B 11
E C 9
F D 10
G E, F 7
H D, G 4

What is the cycle time in minutes?

What is the theoretical number of stations?

Based on Longest Operating Time, were you able to group based on the theoretical number of stations?

and what station is task E assigned to?

Based on your grouping and following the longest operating time rule, is there and opportunity to balance the line more efficiently?

If so, what is the new cycle time

efficiency

and idle time

What is the total actual idle time at all stations over the course of an 16 hour workday for the process based on your answer to letter d.?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

Please like the answer it will encourage me.

Add a comment
Know the answer?
Add Answer to:
You have been asked to balance a flow shop assembly operation to achieve an output rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • As part of a major plant renovation project, the industrial engineering department has been asked to...

    As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:     Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • e As part of a major plant renovation project, the industrial engineering department has been asked...

    e As part of a major plant renovation project, the industrial engineering department has been asked to balance an assembly operation. Assume full 8 hours are available per day. Precedence relationships and tasks times are shown below. If daily demand is 285 units of output, there needs to be workstations to meet the demand. The answer is an integer Task Time (minutes) Cycle time (c) Theoretical minimum number of stations (TM) = Idle time = nc - Et Efficiency (%)...

  • Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line...

    Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...

  • A producer of inkjet printers is planning to add a new line of printers, and you...

    A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...

  • An assembly line is to operate eight hours per day with a desired output of 160...

    An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...

  • IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight...

    IBT Industrial Solutions produces forty units of rack and pinion type steering gears during an eight hour work day. The tasks, times, and predecessor activities involved in the production process are given below. Task Time (minutes) Predecessor(s) A 2 - B 2 A C 8 - D 6 C E 3 B F 10 D, E G 4 F H 3 G a) Determine the cycle time. b) How many work stations are required to produce the forty units of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT