Question

Afinal assembly plant for Dictatape, a popular dictation company, produces the DT, a hand-held dictation unit. There are 400A final assembly plant for Dictatape, a popular dictation company, produces the DT, a hand-held dictation unit. There are 400 minutes available in the final assembly plant for the DT, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table.

Answer parts a through e.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

assembly line balancing: Dictatape a) calculation of cycle time: given: operations time per day = 400 min given: units demandc) determining the actual number of workstations; (using largest performance time rule) activities performance predecessors td) idle time = 7 minutes e) determining the actual efficiency: efficiency = (process time) (lead time) Lead time = CT * NT (5

(Please like the answer it will encourage me.)

Add a comment
Know the answer?
Add Answer to:
A final assembly plant for Dictatape, a popular dictation company, produces the DT, a hand-held dictation...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 4. A company produces a certain product by assembling it at an assembly plant. All the co...

    Problem 4. A company produces a certain product by assembling it at an assembly plant. All the com ponents needed to assemble the product are purchased from a single supplier. A shipment of all the components is received from the supplier each time the assembly plant needs to replenish its inventory of the components. The company incurs a shipping cost of $500 in addition to the purchase price for the components each time this is done. Each time the supplier...

  • Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for...

    Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid filed compartments to provide more stability and better protection against knee, foot, and back injuries Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 62. The information for the tasks is as follows Task Performance Time (mins) Predecessors <UO a-b) The correct precedence...

  • I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc....

    I AM COMPLETELY CONFUSED! Any help would be greatly appreciated. Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first....

  • ... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a...

    ... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: TASK PERFORMANCE TIME (min) TASK MUST FOLLOW TASK LISTED BELOW A,B F, G a) Draw a precedence diagram of this operation. b) What is...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

  • The Mach 10 is a​ one-person sailboat manufactured by Creative Leisure. The final assembly plant is...

    The Mach 10 is a​ one-person sailboat manufactured by Creative Leisure. The final assembly plant is in​ Cupertino, California. The assembly area is available for production of the Mach 10 for 200200 minutes per day. ​(The rest of the time it is busy making other​ products.) The daily demand is 6060 boats. Given the following​ information:                                                                      Task Performance Time​ (mins) Predecessors A 22 minus− B 22 A C 11 A D 11 C E 33 C F 11 C...

  • Widget Manufacturer A plant produces several related models of widgets. Production of each model involves the...

    Widget Manufacturer A plant produces several related models of widgets. Production of each model involves the same machinery. The plant produces each model in separate production runs. Each production run has significant setup costs and the cost per setup is the same for every model. Also, the assembly of each unit requires hand labor (direct labor). The following costs were incurred during a recent year: a) direct labor costs. b) costs of placing orders to procure parts. c) costs of...

  • 3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair...

    3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...

  • 1 The Quality Managem ent Depact ent is asiced so balance a sensed assembly line that...

    1 The Quality Managem ent Depact ent is asiced so balance a sensed assembly line that wwall turn out 400 ndeotapes per day There will be eight worlong hours in each day The detailed nformation ss given in the table below Task Time (minutes) 0 4 1 0 0 01 Total The diagram is as folow ()Determ ine the calculated cycle time b) What is the minmum number of stations needed (e) Compute the efficiency of the system 2 A...

  • Case Studies Jackson Manufacturing Company Kathleen McFadden, vice president of operations at Jackson Manufacturing Company, has...

    Case Studies Jackson Manufacturing Company Kathleen McFadden, vice president of operations at Jackson Manufacturing Company, has just received a request for quote (RFQ) from DeKalb Electric Supply for 400 units per week of a motor armature. The components are standard and either easy to work into the existing production schedule or readily available from established suppliers on a JIT basis. But there is some difference in assembly. Ms. McFadden has identified eight tasks that Jackson must perform to assemble the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT