Man is begins construction of a warehouse on July , 20X6. The project was completed on March 31, 20X7. No new loans were required to funds construction. Man is does have the following two interest-bearing liabilities that were outstanding throughout the sonctrcion period:
$2,000,00, 8% note
$8,000,000, 4% bonds
Construction expenditures incurred were as follow:
July 1, 20X6 $400,000
September 30, 20X6 $ 600,000
November 30, 20X8 $600,000
January 30, 20X7 $540,000
The Company’s Fiscal years-end is December 31.
Required:
Calcuate the amount of interest capitalized for 20X6 and 20X7.
1)Calculation of average interest rate:
Amount | Rate | Interest expense | |
Note | 2000000 | 8% | 2000000*8%=160000 |
Bond | 8000000 | 4% | 8000000*4%=320000 |
Total loan outstanding | 10,000,000 | Total interest | 480000 |
Average interest rate =480000/10000000 = 4.80%
2)Calculation of weighted average capital expenditure for 2016:
Date | Amount | period of outstanding(out of 12 months) | Average accumulated expenditure |
1July 20x6 | 400000 | 6/12 [1July-31Dec] | 400000*6/12=200000 |
Sep 30 20x6 |
600000 | 3/12 | 600000*3/12=150000 |
Nov 30 20x6 | 600000 | 1/12 | 600000*1/12=50000 |
1600000 | |||
Total average expenditures | 400000 |
Calculation of weighted average capital expenditure for 2016:
Date | Amount | period of outstanding(out of 12 months) | Average accumulated expenditure |
Beginning balance | 1600000 | 3/12 [Jan -31March] | 1600000*3/12=400000 |
30Jan 2017 | 540000 | 2/12 [Feb-31march] | 90000 |
Total | 490000 |
3)Calculation of interest capitalized :
for 2016 : Average accumulated expenditures*average rate
= 400000*4.80%
=19200
For 2017 : 490000*4.80%
= 23520
Man is begins construction of a warehouse on July , 20X6. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 January 30, 2022 $ 400,000 600,000 600,000 540,000 The company's fiscal year-end is December 31. Required: Calculate...
Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The company's fiscal year-end...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...
8 of 10 Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 430,000 September 30, 2021 630,000 November 30, 2021 630,000 January 30, 2022 570,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...