Big MAC Contractors began work on a contract to build a new student union on the St. Maximo University campus for $910,000. Information concerning the project follows:
Year 1 |
Year 2 |
Year 3 |
|
Percentage of work completed |
25% |
35% |
40% |
Costs incurred during the year |
$172,000 |
$248,000 |
$180,000 |
Progress billings during the year |
160,000 |
360,000 |
380,000 |
Cash collected during the year |
130,000 |
340,000 |
430,000 |
How much revenue should Big MAC recognize during Year 1 if it uses the percentage of completion method?
Group of answer choices
$227,500
$900,000
$ 77,500
$160,000