Fletcher Company collected the following data regarding production of one of its products. Compute the total direct labor cost variance. Direct labor standard (2 hrs. @ $12.75/hr.) $ 25.50 per finished unit Actual direct labor hours 101,900 hrs. Actual finished units produced 50,000 units Actual cost of direct labor $ 1,355,750
Actual cost of direct labor | 1355750 | |
Less: Standard cost of direct labor | 1275000 | =50000*25.50 |
Total direct labor cost variance | 80750 | Unfavorable |
Fletcher Company collected the following data regarding production of one of its products. Compute the total...
Fletcher Company collected the following data regarding production of one of its products. Compute the total direct labor cost variance. Direct labor standard (2 hrs. @ $12.75/hr.) $ 25.50 per finished unit Actual direct labor hours 60,400 hrs. Actual finished units produced 30,000 units Actual cost of direct labor $ 844,750
Help Save MC Qu. 143 Fletcher Company collected the following... Fletcher Company collected the following data regarding production of one of its products. Compute the direct labor efficiency variance. Direct labor standard (2 hrs. @ $12.75/hr.) $ 25.50 per finished unit Actual direct labor hours 81,500 hrs. Actual finished units produced 40,000 units Actual cost of direct labor $1,100,250 Multiple Choice O $19,125 favorable O $80.250 favorable O O $61125 favorable $19.125 unfavorable.
Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead spending variance. Direct labor standard (3.00 hrs. @ $19.20/hr.) $ 57.60 per finished unit Actual direct labor hours 86,400 hrs. Budgeted units 28,900 units Actual finished units produced 27,900 units Standard variable OH rate (1.50 hrs. @ $12.00/hr.) $ 18.00 per finished unit Standard fixed OH rate ($260,100/28,900 units) $ 9.00 per unit Actual cost of variable overhead costs incurred $ 499,600 Actual...
Saved Help Save & MC Qu. 143 Fletcher Company collected the following... Fletcher Company collected the following data regarding production of one of its products. Compute the direct labor efficiency variance. Direct labor standard (2 hrs. e $12.75/hr.) $ 25.50 per finished unit 81,500 hrs. 40,000 units $1,100,250 Actual direct labor hours Actual finished units produced Actual cost of direct labor Multiple Choice $19,125 favorable. nces $80,250 favorable. $61,125 favorable. $19.125 unfavorable. Next >
Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.40/hr.) $ 24.80 per finished unit Actual direct labor hours 96,500 hrs. Budgeted units 56,000 units Actual finished units produced 47,500 units Standard variable OH rate (2 hrs. @ $15.00/hr.) $ 30.00 per finished unit Standard fixed OH rate ($526,400/56,000 units) $ 9.40 per unit Actual cost of variable overhead costs incurred $ 1,417,000 Actual...
Fletcher Company collected the following data regarding production of one of its products. Compute the direct materials quantity variance. Direct materials standard (6 lbs. @ $2/lb.) $12 per finished unit Actual direct materials used 206,700 lbs. Actual finished units produced 34,000 units Actual cost of direct materials used $411,030 $2,370 unfavorable. $3,030 unfavorable. $2,370 favorable. $5,400 unfavorable $3030 favorable
Fletcher Company collected the following data regarding production of one of its products. Compute the direct materials quantity variance. Direct materials standard (6 lbs. e $2/1b.) Actual direct materials used Actual finished units produced Actual cost of direct materials used 12 per finished unit 279,300 lbs. 46,000 units $556,110 Multiple Choice O $2,490 unfavorable. $4.10 unfavorable. $2,490 favorable. $6.600 unfavorable. $410 favorable.
Gala Enterprises reports the following information regarding the production on one of its products for the month. $8 per finished unit 390,000 lbs. Direct materials standard (4 lbs. @ $2/lb.) Actual direct materials used Actual finished units produced Actual cost of direct materials used 90,000 units $770,000 Requirement 1: Compute the direct materials cost variance and identify as either F for favorable or U for unfavorable. Cost variance .F/U Requirement 2: Compute the direct materials price variance and identify as...
PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.20/hr.) Actual hours worked Actual rate per hour $ 24.80 per unit 12,050 $ 6.30 Multiple Choice . $12,050 favorable 0 $10.885 unfavorable. 0 $10,885 favorable. 0 $1,400 favorable. O $1,400 unfavorable. Fletcher Company collected the following data regarding...
PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...