chapter 15. problem 19
Calculate variable cost variances—explain results The standards for one case of Springfever Tonic are as follows:
Direct materials . . . . . . . . . . . . . . . . . . . . 4 lb @ $5.00/lb = $20
Directlabor....................... 3hr@$13.00/hr =$39 Variable overhead (based
ondirectlaborhours) ............. 3hr@$6.00/hr =$18
During the week ended August 28, the following activity took place:
7,400 lb of raw materials were purchased for inventory at a cost
of $4.95 per pound.
2,000 cases of finished product were produced.
8,300 lb of raw materials were used.
5,800 direct labor hours were worked at a total cost of $78,300. $35,670 of actual variable overhead costs were incurred.
Required:
Calculate each of the following variances and provide plausible explanations for the results:
Price variance for raw materials purchased.
Raw materials usage variance.
Direct labor rate variance.
Direct labor efficiency variance.
Variable overhead spending variance.
Variable overhead efficiency variance.
1) | for direct materials | |||||||||
a. | price and quantity variance | |||||||||
Standard | - | Actual | * | Actual | = | Variance | ||||
price | price | quantiy | ||||||||
materials price variance | 5 | 4.95 | 7,400 | = | 370 | F | ||||
standard | - | Actual | * | Standard | = | Variance | ||||
qty | qty | price | ||||||||
materials quantity variance | 8000 | 8,300 | 5 | 1500 | U | |||||
2) | for direct labor | |||||||||
Standard | - | Actual | * | Actual | = | Variance | ||||
rate | rate | hours | ||||||||
labor price variance | 13 | 13.5 | 5800 | = | 2900 | U | ||||
standard | - | Actual | * | Standard | = | Variance | ||||
hours | hours | rate | ||||||||
labor efficiency variance | 6000 | 5,800 | 13 | 2600 | F | |||||
3) | for variable overhead | |||||||||
Standard | - | Actual | * | Actual | = | Variance | ||||
rate | rate | hours | ||||||||
Variable overhead rate | 6 | 6.15 | 5,800 | = | 870 | U | ||||
standard | - | Actual | * | Standard | = | Variance | ||||
hours | hours | rate | ||||||||
variable overhead efficiency | 6000 | 5,800 | 6 | 1200 | F | |||||
chapter 15. problem 19 Calculate variable cost variances—explain results The standards for one case of Springfever...
The standards for one case of liquid weed killer are as follows: Direct materials 5 lb @ $ 6.80 /lb Direct labor 2.4 hr @ $ 14.00 /hr Variable overhead (based on machine hours) 1.5 hr @ $ 4.50 /hr During the week ended May 6, the following activity took place: 2,910 machine hours were worked. 11,400 lb of raw material were purchased for inventory at a total cost of $80,940. 1,900 cases of finished product were produced. 9,260 lb...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $13,640 Direct material Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead Standard (0.5 hr. @ $4/hr.) Actual Total 13,426 $15 4,200 $31,266 Assume that...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material $6 Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor $13,640 $7 Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead 13,426 Standard (0.5 hr. @ $4/hr.) Actual 4,200 $31,266 Total $15...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) Actual 6,200 Total $71,738 Assume...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (3 lb. @ $2.00/lb.) $6 Actual (6,200 lb. @ $2.20/lb.) $13,640 Direct labor Standard (0.5 hr. @ $14/hr.) $7 Actual (980 hrs. @ $13.70/hr.) 13,426 Variable overhead Standard (0.5 hr. @ $4/hr.) $2 Actual - 4,200 Total...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) $3 6,200 Actual $34 $71,738...
PQ7a Saved Help Save & Exit Submit 1 Direct materials 6.00 lbs @ $5.00/lb =$ 30 Direct labor 5.00 hrs @ $12.00/hr = 60 Variable overhead (based on direct labor hours) 5.00 hrs. @ $6.00/hr = 30 0.6 points During the week ended March 28, the following activity took place: X 01:18:24 21,000 lbs. of raw materials were purchased for inventory at a cost of $4.95 per pound. 2,700 cases of finished product were produced. 16,500 lbs. of raw materials...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $38 $83,160 $17 Direct material Standard (2 lb. @ $19.00/lb.) Actual (4,200 lb. @ $19.80/lb.) Direct labor Standard (0.5 hr. @ $34/hr.) Actual (950 hrs. @ $33.00/hr.) Variable overhead Standard (0.5 hr. @ $16/hr.) Actual Total 31,350 $8 16,450 $130,960...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $34 $74,760 Direct material Standard (2 lb. @ $17.00/lb.) Actual (4,200 lb. @ $17.80/lb.) Direct labor Standard (0.5 hr. @ $32/hr.) Actual (950 hrs. @ $31/hr.) Variable overhead Standard (0.5 hr. @ $14/hr.) $16 29,450 $7 Actual 14,450 $118,660 Total...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $18.00/lb.) $36 Actual (4,200 lb. @ $19/lb.) $79,800 Direct labor Standard (0.5 hr. @ $33/hr.) $16.50 Actual (950 hrs. @ $32.20/hr.) 30,590 Variable overhead Standard (0.5 hr. @ $15/hr.) $7.50 Actual 15,450 Total $60...