Question

On January 1, Year 1, Chester Co. began construction of a small building. The following expenditures...

On January 1, Year 1, Chester Co. began construction of a small building. The following expenditures were incurred for construction in Year 1: January 1 $125,000 May 1 $104,000 Oct 1 $124,000 December 31 $200,000 The building was not completed in Year 1. On January 1, Year 2, Chester spent another $180,000 on construction. The building was then completed and occupied on January 31, Year 2. To help pay for construction, $80,000 was borrowed on January 1, Year 1 on a 15%, three-year note payable. The entire $80,000 debt will remain outstanding until Year 4. Chester has no other debt. Calculate the weighted-average accumulated expenditures for Year 2.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Weighted average accumulated expenditures

Date expenditure Weighted average expenditure
Jan 1 125000 125000*13/12 135417
May 1 104000 104000*9/12 78000
Oct 1 124000 124000*4/12 41333
Dec 31 200000 200000*1/12 16667
Total 271417

Weighted average accumulated expenditure for year 2 = $271417

Thank You So Much! Please Rate this answer as you wish.("Thumbs Up")

Add a comment
Know the answer?
Add Answer to:
On January 1, Year 1, Chester Co. began construction of a small building. The following expenditures...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ex. 10-133—Capitalization of interest. On March 1, Mocl Co. began construction of a small building. The...

    Ex. 10-133—Capitalization of interest. On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred for construction: March 1 $ 150,000 April 1 $ 148,000 May 1 360,000 June 1 540,000 July 1 200,000 The building was completed and occupied on July 1. To help pay for construction $100,000 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $1,000,000, 10% note issued two...

  • On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred...

    On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred for construction: March 1 $226,560 Apri1 219,840 June1 803,880 July 1306,480 541,320 | The building was completed and occupied on July 1 . To help pay for construction $151,440 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $2,000,000, 10% note issued two years ago. Calculate the weighted-average accumulated expenditures. (Do not...

  • On March 1, Nielson LLC. began construction of a small building. The following expenditures were incurred...

    On March 1, Nielson LLC. began construction of a small building. The following expenditures were incurred for construction: March 1 $ 225,000 April 1 540,000 May 1 300,000 June 1 $ 222,000 July 1 810,000 The building was completed and occupied on July 1. To help pay for construction $150,000 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $1,500,000, 10% note issued two years ago. Instructions (SHOW...

  • Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October...

    Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...

  • Turkey Incorporated began constructing a building on the 1st of January and completed construction on the...

    Turkey Incorporated began constructing a building on the 1st of January and completed construction on the 31st of December, of the same year. Costs on the construction during this one-year period were as follows: March 1 $3,200 August 1 2,280 Dec 31 4,000 On January 1, Turkey borrowed $1,600 to finance the construction. They signed a 5-year, 12% note when they borrowed the money. Additional debt Turkey owed during the entire year included a 10%, 3-year, $1,000 note and an...

  • Bonita Industries is constructing a building. Construction began on January 1 and was completed on December...

    Bonita Industries is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6440000 on March 1, $5260000 on June 1, and $8850000 on December 31. Bonita Industries borrowed $3190000 on January 1 on a 5-year, 11% note to help finance construction of the building. In addition, the company had outstanding all year a 9%, 3-year, $6440000 note payable and an 10%, 4-year, $12650000 note payable. What are the weighted-average accumulated expenditures? $11700000 $9860000...

  • Bob Company is constructing a building. Construction began on January 1 and was completed on December...

    Bob Company is constructing a building. Construction began on January 1 and was completed on December 31. Construction expenditures were $900,000 on April 1; $400,000 on June 30; $510,000 on September 1; and $120,000 on December 1. Bob Company borrowed $700,000 at 9% on January 1 to help finance construction of the building. In addition, the company had outstanding all year a 5%, 3-year, $100,000 note payable and a 6%, 2-year, $200,000 note payable. Instructions a) Determine the amount of...

  • Ex. 10-132-Weighted-Average Accumulated Expenditures On April 1, Paine Co. began construction of a small building. Payments...

    Ex. 10-132-Weighted-Average Accumulated Expenditures On April 1, Paine Co. began construction of a small building. Payments of $180,000 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building by completing the schedule below: Capitalization Date Period Expenditures Weighted-Average Expenditures

  • Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its...

    Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was outstanding for the...

  • Turkey Incorporated began constructing a building on the 1st of January and completed construction on the...

    Turkey Incorporated began constructing a building on the 1st of January and completed construction on the 31st of December, of the same year. Costs on the construction at various points throughout this one-year period totaled $9,480. Assume the weighted average accumulated expenditures is $3,000. On January 1, Turkey borrowed $1,600 to finance the construction. They signed a 5-year, 12% note when they borrowed the money. Additional debt Turkey owed during the entire year included a 10%, 3-year, $1,000 note and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT