1. Calculate the Net Present Value(NPV) of the following cash flow stream if the required rate is 12%?
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash Flow | (230,000) | 60,000 | 60,000 | 60,000 | 60,000 | 60,000 |
Given that the required return is 12%.
Net present value is the difference between the initial investment
and the present value of the future cash flows.
With the given cash flows, we can determine the net present value
using excel as follows:
Answer: Hence, the net present value is $11684.44
1. Calculate the Net Present Value(NPV) of the following cash flow stream if the required rate...
CDEFGH Complete the following problems: (1) Calculate the Net Present Value (NPV) of the following cash flow stream if the required rate is 12%: Year Cash Flow 0 (230,000) 1 60,000 2 60.000 60.000 60.000 60,000 Is this a good project for the business to accept? Explain why or why not. wer (2) Calculate the Net Present Value (NPV) of the following cash flow projections based on a required rate of 10.5% Cash Flow Year Cash Flow (120,00) 350 (120,000)...
What is the Net Present Value of the following cash flow stream? Year Cash Flow 0 -$6,119 1 $1,333 2 $1,395 3 $1,160 4 $2,709 Assume an interest rate of 20%
26- What is the present value of the following cash flow stream at a rate of 13.5%? Years: 0 1 2 3 4 CFs: $0 $1,500 $3,000 $4,500 $6,000 27- What is the future value of the following cash flow stream at a rate of 13.5%? Years: 0 1 2 3 4 CFs: $0 $1,500 $3,000 $4,500 $6,000
What is the present value of the following cash-flow stream if the interest rate is 5%? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Year Cash Flow 1 $ 250 2 450 3 350 Present value $
1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...
What is the net present value (NPV) of a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (14,000) 1 $ 3,000 2 $ 3,000 3 $ 3,000 4 $ 3,000 5 $ 3,000 6 $ 3,000
What is the net present value (NPV) of a project that has the following cash flows? The required return is 10.0% Year 0 1 2 Cash Flow $ (5,000) $2,000 $ 2,000 $ 2,000 $3,000 $1,000 $1,000 3 4 5 6
1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Cute Camel Woodcraft Company is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $550,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $450,000...
What is the present value of the following cash flow stream at a rate of 11.00%?Years01234CFS$0$75$225$0$300 a $465.71 b. $362.72 c. $447.80 d. $501.54 e. $52393
1. Calculate the net present value (NPV) of a project with the following stream of CFs: C, through Cls are all equal to $800, C19 = $300, and C20 = -$800 (notice the minus). The initial investment is $4000. The appropriate discount rate is 10%.