Question

Question 3 (6 marks) Mendel Allison Company adopted a standard cost system several years ago. The...

Question 3 (6 marks) Mendel Allison Company adopted a standard cost system several years ago. The standard costs for the prime costs of its single product follow: Material: 10 kilograms @ R4.50 per kilogram R45.00 Labour: 6 hours @ R8.50 per hour R51.00 The following operating data were taken from the records for November: 1. Units completed: 5,800 units 2. Budgeted output: 6,000 units 3. Materials purchased: 60,000 kilograms 4. Total actual labour costs: R306,600 5. Actual hours of labour: 36,500 hours 6. Material usage variance: R2,250 U 7. Total material variance: R450 U Compute the following: A. Labour rate variance (1½) B. Labour efficiency variance (1½) C. Actual kilograms of material used in the production process (1½) D. Actual cost paid per kilogram of material (1½)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

A. Labor rate variance:

=Actual Hours×(Actual cost - Standard cost)

=36500 hrs ×($8.40/hr* - $8.50/ hr)

=$3,650 F

*$306600 labor cost/36500 hours worked=$8.40/hr

B. Labor efficiency variance:

=standard cost×(Actual hours - Standard hours)

=$8.50/hr × (36500 hrs - 34800 hrs*)

=$14,450 U

C.

Material usage variance= Standard cost× ( actual quantity - standard quantity)

$2250 =$4.50/kg × ( Actual quantity - 58000 kg*)

500 kg= Actual quantity -58000 kg

Actual quantity=58500 kg

*5800 units × 10 kg per unit=58000 kg

D.

Total material variance= material usage variance+ material price variance

450=2250+ material price variance

Material price variance=$1800 F

Material price variance= (Actual cost - Standard cost) × Actual quantity purchased

-1800=(Actual cost - $4.50/ kg) × 60000 kg

- $0.03 (rounded) = Actual cost - $4.50/ kg

Actual cost=$4.47 per kg

Add a comment
Know the answer?
Add Answer to:
Question 3 (6 marks) Mendel Allison Company adopted a standard cost system several years ago. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Dash Company adopted a standard costing system several years ago. The standard costs for the prime...

    Dash Company adopted a standard costing system several years ago. The standard costs for the prime costs (.e., direct materials and direct labor) of its single product are: Material Labor (5 kilograms x $6.00 per kilogram) (6 hours x $16.00 per hour) $30.00 96.00 All materials are added at the beginning of processing. The following data were taken from the company's records for November: In-process beginning inventory In-process ending inventory Units completed Budgeted output Purchases of materials Total actual direct...

  • Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction...

    Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction with its process cost system. The per-unit standard costs for direct materials and direct labor for its single product are as follows: Materials:(3 kilograms x $8 per kilogram) (3 hours x $18 per hour) 24 Labor: 54 All materials are issued at the beginning of processing. The operating data shown below were taken from the records for July In-process beginning inventory In-process ending inventory-90%...

  • Shade Company adopted a standard cost system several years ago. The standard costs for direct labor...

    Shade Company adopted a standard cost system several years ago. The standard costs for direct labor and direct materials for its single product are as follows: Materials (5 kilograms $12/kilogram) = $60/unit, direct labor (3.5 hours/unit * $20/hour) = $70/unit. All materials are issued at the beginning of processing. The operating data shown below were taken from the records for December: In-process beginning inventory In-process ending inventory-80% complete as to labor Units completed during the period Budgeted output Purchases of...

  • Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction...

    Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction with its process cost system. The per-unit standard costs for direct materials and direct labor for its single product are as follows: $ 88 Materials: (8 kilograms x $11 per kilogram) Labor: (7 hours x $18 per hour) $ 126 All materials are issued at the beginning of processing. The operating data shown below were taken from the records for July In-process beginning inventory...

  • Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction...

    Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction with its process cost system. The per-unit standard costs for direct materials and direct labor for its single product are as follows: ed Materials. (3 kilograms x $8 per kilogram) 3 hours $18 Labor: per hour) 5 4 All materials are issued at the beginning of processing. The operating data shown below were taken from the records for July In-process beginning none inventory In-process...

  • Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction...

    Machine Builders Inc. adopted a standard cost system several years ago that it uses in conjunction with its process cost system. The per-unit standard costs for direct materials and direct labor for its single product are as follows: Materials: (5 kilograms × $10 per kilogram) $ 50 Labor: (4 hours × $13 per hour) $ 52 All materials are issued at the beginning of processing. The operating data shown below were taken from the records for July: In-process beginning inventory...

  • Question 3: Variance Analysis (20 marks in total) You have introduced a standard cost accounting system...

    Question 3: Variance Analysis (20 marks in total) You have introduced a standard cost accounting system for FOL. The following standard costs have been developed for the Cattle drench. Direct materials (1 kilogram) $ 20 Direct Labour (.25 hours) $ 15 Overhead (DLH basis) $ 3 $ 38 Production and cost information for May was: Actual direct material purchased 1200 kilograms Actual direct materials issued 900 kilograms Actual output 800 kilograms Actual cost of materials purchased $ 25,500 Actual direct...

  • Problem 14-48 Standard Costs in Process Costing; All Variances and Journal Entries [LO 14-3, 14-5] Dash...

    Problem 14-48 Standard Costs in Process Costing; All Variances and Journal Entries [LO 14-3, 14-5] Dash Company adopted a standard costing system several years ago. The standard costs for the prime costs (i.e., direct materials and direct labor) of its single product are: Material (7 kilograms × $6.00 per kilogram) $ 42.00 Labor (5 hours × $18.80 per hour) 94.00 All materials are added at the beginning of processing. The following data were taken from the company’s records for November:...

  • please let me know if the additional info was helpful In-process beginning inventory In-process ending inventory...

    please let me know if the additional info was helpful In-process beginning inventory In-process ending inventory Units completed Budgeted output Purchases of materials Total actual direct labor costs Actual direct labor hours Materials usage variance Total materials variance None 700 units, 70% complete as to direct labor 6,200 units 6,6ee units 56,000 kilograms $ 668,000 39,200 hours 2,100 Unfavorable 700 Unfavorable Required: 1. Compute for November: a. The direct labor efficiency variance. Is this variance favorable (F) or unfavorable (U)?...

  • Materials and Labour Variances At the beginning of the year, Shults Company had the following standard...

    Materials and Labour Variances At the beginning of the year, Shults Company had the following standard cost sheet for one of its plastic products: $20.00 Direct materials (5 kg @ $4.00) Direct labour (2 hrs. @ $11.25) 22.50 Standard prime cost per unit $42.50 The actual results for the year are as follows: a. Units produced: 175,000. b. Materials purchased: 930,000 kilograms @ $4.10. C. Materials used: 925,000 kilograms. d. Direct labour: 362,500 hours @ $11.15. Required: 1. Compute price...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT