Question

Which of the following variances exists only under absorption costing? options: production-volume variance efficiency variances spending...

Which of the following variances exists only under absorption costing?
options:

production-volume variance


efficiency variances


spending variance


sales-volume variance

Question 2 (0.33333333 points)
General Media manufactures cassettes and CDs in separate divisions utilizing one plant location. The following data have been prepared for review.


Fixed operation costs

$900,000

Practical capacity

2,500 hours

Budgeted usage:


Cassette Division

2,000 hours

CD Division

350 hours

Budgeted variable cost per hour

$400 per hour


What is the fixed cost per year and the variable cost per hour, respectively, for the General Media Cassette Division using the dual-rate method, assuming that the allocation bases are capacity for fixed costs and budgeted capacity for variable costs?

options:

$765,958 rounded and $360


$720,000 and $360


$720,000 and $400


$765,958 rounded and $400

Question 3 (0.33333333 points)
The relative amount of inputs used to reach a given level output is a measure of which of the following?

options:

selling price


efficiency


effectiveness


marketing efforts

Question 4 (0.33333333 points)
Which of the following is likely to be related to an unfavorable direct materials rate variance?

options:

Standard costs were determined correctly.


Materials were purchased based on a competitive bid.


unexpected price decreases in direct materials


the negotiating skills of the marketing manager

Question 5 (0.33333333 points)
In a firm's value chain downstream costs are categorized as

options:

customer service costs.


production costs.


design costs
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans-1 The correct option is-production volume variance.

2-the correct option is-$720000 and $400.

3-the correct option is-efficiency.

4-the correct option is -the negotiating skills of the marketing manager

5-the correct option is -customer service costs

Add a comment
Know the answer?
Add Answer to:
Which of the following variances exists only under absorption costing? options: production-volume variance efficiency variances spending...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual...

    2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual Cost $ $ 0 0 0 0 3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllable variance Fixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance Check my work 1 ! Required information 12.5 [The following information applies to the questions displayed below.] points Trico Company set the following standard unit costs...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. Solve for: Variable Overhead Spending Variance Variable Overhead Efficiency Variance Variable Overhead Total...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2016, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2016. calculate the following variances: Material Price Variance Materials Quantity Variance Total Materials Variance...

  • Milberg Co. uses absorption costing and standard costing to improve cost control. In 2020, the total...

    Milberg Co. uses absorption costing and standard costing to improve cost control. In 2020, the total budgeted overhead rate was $1.55 per direct labour hour. When preparing the budget, Milberg expected a monthly activity level of 10,000 direct labour hours. The monthly variable overhead cost budgeted for this level of activity was $9,500. The following data on actual results are provided for the month of November 2020. Materials purchased 20,000 units Direct labour costs incurred $36,000 Total of direct labour...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $811,800, of which $585,480 is fixed overhead. A total of 119,500 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,700, and...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 129,000 units requiring 516,000 direct labor hours. (Practical capacity is 536,000 hours.) Annual budgeted overhead costs total $861,720, of which $608,880 is fixed overhead. A total of 119,000 units using 514,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,100, and...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 126,000 units requiring 504,000 direct labor hours. (Practical capacity is 524,000 hours.) Annual budgeted overhead costs total $826,560, of which $599,760 is fixed overhead. A total of 119,400 units using 502,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $260,100, and...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 124,000 units requiring 496,000 direct labor hours. (Practical capacity is 516,000 hours.) Annual budgeted overhead costs total $828,320, of which $590,240 is fixed overhead. A total of 119,200 units using 494,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,300, and...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 121,000 units requiring 484,000 direct labor hours. (Practical capacity is 504,000 hours.) Annual budgeted overhead costs total $808,280, of which $575,960 is fixed overhead. A total of 119,000 units using 482,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,800, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT