Schedule of Activity Costs |
Quality Control Activities | Activity Cost |
Process audits | $48,800 |
Training of machine operators | 27,000 |
Processing returned products | 20,600 |
Scrap processing (disposal) | 26,800 |
Rework | 6,400 |
Preventative maintenance | 28,700 |
Product design | 44,100 |
Warranty work | 6,900 |
Finished goods inspection | 22,100 |
From the above schedule of activity costs, determine the appraisal costs.
a.$118,300
b.$70,900
c.$48,800
d.$170,700
Appraisal cost = Process audits + Finished goods inspection
= $48800 + 22100
= $70900
Option b. is correct answer.
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $48,800 Training of machine operators...
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,500 Training of machine operators 27,400 Processing returned products 18,100 Scrap processing (disposal) 25,300 Rework 7,900 Preventative maintenance 27,100 Product design 41,100 Warranty work 9,100 Finished goods inspection 23,300 From the above schedule of activity costs, determine the appraisal costs. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,200 Training of machine operators 28,200 Processing returned products 18,900 Scrap processing (disposal) 26,600 Rework 6,700 Preventative maintenance...
Schedule of Activity Costs Quallty Control Activities Activity Cost Process audits $48,900 Training of machine operators 26,300 Processing returned products 19,500 Scrap processing (disposal) 25,800 Rework 7,800 Preventative maintenance 28,300 41,800 Product design Warranty work 6,900 Finished goods inspection 22,600 From the provided schedule of activity costs, determine the external failure costs. a. $60,000 b. $26,400 c. $86,300 d. $21,120
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators 28,000 Processing returned products 19,000 Scrap processing (disposal) 25,000 Rework 8,000 Preventative maintenance 30,000 Product design 46,000 Warranty work 12,000 Finished goods inspection 23,000 From the above schedule of activity costs, determine the prevention costs. a.$30,000 b.$74,000 c.$104,000 d.$76,000
12. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,800 Training of machine operators 27,800 Processing returned products 20,000 Scrap processing (disposal) 26,100 Rework 5,600 Preventative maintenance 30,200 Product design 45,000 Warranty work 6,600 Finished goods inspection 23,400 From the above schedule of activity costs, determine the appraisal costs. a.$177,200 b.$50,800 c.$74,200 d.$120,300
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,100 Training of machine operators 25,000 Processing returned products 15,100 Scrap processing (disposal) 24,400 Rework 7,300 Preventative maintenance 30,800 Product design 42,600 Warranty work 6,100 Finished goods inspection 22,800 From the above schedule of activity costs, determine the non-value-added costs. a.$112,200 b.$52,900 c.$224,200 d.$46,800
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators 28,000 Processing returned products 19,000 Scrap processing (disposal) 25,000 Rework 8,000 Preventative maintenance 30,000 Product design 46,000 Warranty work 12,000 Finished goods inspection 23,000 From the above schedule of activity costs, determine the value-added costs. a.$177,000 b.$104,000 c.$191,000 d.$156,000
Miller and Sons' static budget for 10,300 units of production includes $35,400 for direct materials, $52,400 for direct labor, variable utilities of $6,900, and supervisor salaries of $15,700. A flexible budget for 14,000 units of production would show Round your final answer to the nearest dollar. Do not round interim calculations, a. direct materials of $48,117, direct labor of $71,223, utilities of $9,379, and supervisor salaries of $15,700 Ob the same cost structure in total Octotal variable costs of $110,400...