Question

Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,500 Training of machine operators...

Schedule of Activity Costs
Quality Control Activities Activity Cost
Process audits $49,500
Training of machine operators 27,400
Processing returned products 18,100
Scrap processing (disposal) 25,300
Rework 7,900
Preventative maintenance 27,100
Product design 41,100
Warranty work 9,100
Finished goods inspection 23,300

From the above schedule of activity costs, determine the appraisal costs.

Schedule of Activity Costs
Quality Control Activities Activity Cost
Process audits $49,200
Training of machine operators 28,200
Processing returned products 18,900
Scrap processing (disposal) 26,600
Rework 6,700
Preventative maintenance 32,000
Product design 40,800
Warranty work 7,200
Finished goods inspection 23,800

From the above schedule of activity costs, determine the total activity cost.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

From the above schedule of activity costs, determine the appraisal costs.

Process audits + Processing returned products + Rework = 49500 + 18100 + 7900 = $75500

From the above schedule of activity costs, determine the total activity cost.

Process audits + Training of machine operators + Processing returned products + Processing returned products + Rework + Preventative maintenance + Product design + Warranty work + Finished goods inspection

49200 + 28200 + 18900 + 26600 + 6700 + 32000 + 40800 + 7200 + 23800 = $233400

Add a comment
Know the answer?
Add Answer to:
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,500 Training of machine operators...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators...

    Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators 28,000 Processing returned products 19,000 Scrap processing (disposal) 25,000 Rework 8,000 Preventative maintenance 30,000 Product design 46,000 Warranty work 12,000 Finished goods inspection 23,000 From the above schedule of activity costs, determine the prevention costs. a.$30,000 b.$74,000 c.$104,000 d.$76,000

  • Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $48,800 Training of machine operators...

    Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $48,800 Training of machine operators 27,000 Processing returned products 20,600 Scrap processing (disposal) 26,800 Rework 6,400 Preventative maintenance 28,700 Product design 44,100 Warranty work 6,900 Finished goods inspection 22,100 From the above schedule of activity costs, determine the appraisal costs. a.$118,300 b.$70,900 c.$48,800 d.$170,700

  • Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,100 Training of machine operators...

    Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,100 Training of machine operators 25,000 Processing returned products 15,100 Scrap processing (disposal) 24,400 Rework 7,300 Preventative maintenance 30,800 Product design 42,600 Warranty work 6,100 Finished goods inspection 22,800 From the above schedule of activity costs, determine the non-value-added costs. a.$112,200 b.$52,900 c.$224,200 d.$46,800

  • Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators...

    Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators 28,000 Processing returned products 19,000 Scrap processing (disposal) 25,000 Rework 8,000 Preventative maintenance 30,000 Product design 46,000 Warranty work 12,000 Finished goods inspection 23,000 From the above schedule of activity costs, determine the value-added costs. a.$177,000 b.$104,000 c.$191,000 d.$156,000

  • 12. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,800 Training of machine...

    12. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,800 Training of machine operators 27,800 Processing returned products 20,000 Scrap processing (disposal) 26,100 Rework 5,600 Preventative maintenance 30,200 Product design 45,000 Warranty work 6,600 Finished goods inspection 23,400 From the above schedule of activity costs, determine the appraisal costs. a.$177,200 b.$50,800 c.$74,200 d.$120,300

  • Schedule of Activity Costs Quallty Control Activities Activity Cost Process audits $48,900 Training of machine operators...

    Schedule of Activity Costs Quallty Control Activities Activity Cost Process audits $48,900 Training of machine operators 26,300 Processing returned products 19,500 Scrap processing (disposal) 25,800 Rework 7,800 Preventative maintenance 28,300 41,800 Product design Warranty work 6,900 Finished goods inspection 22,600 From the provided schedule of activity costs, determine the external failure costs. a. $60,000 b. $26,400 c. $86,300 d. $21,120

  • Cost of Quality Report Meagher Solutions Inc. manufactures memory chips for personal computers. An activity analysis...

    Cost of Quality Report Meagher Solutions Inc. manufactures memory chips for personal computers. An activity analysis was conducted, and the following activity costs were identified with the manufacture and sale of memory chips: a. Identify the cost of quality classification for each activity. Quality Activities Activity Cost Quality Cost Classification Correct shipment errors $150,000 Disposing of scrap 95,000 Emergency equipment maintenance 125,000 Employee training 50,000 Final inspection 80,000 Inspecting incoming materials 60,000 Preventive equipment maintenance 40,000 Processing customer returns 90,000...

  • 1. A number of activities that are a part of a company's quality control system are...

    1. A number of activities that are a part of a company's quality control system are listed below. Classify the costs associated with each of these activities into one of the following categories: prevention cost, appraisal cost, internal failure cost, or external failure cost. Activities Cost a. Product testing. b. Product recalls c. Rework labor and overhead. d. Quality circles e. Downtime caused by defects f. Cost of field servicing 0 Inspection of goods h. Quality engineering Warranty repairs Statistical...

  • 1) As quality engineer you are asked to organize the following cost items into the categories...

    1) As quality engineer you are asked to organize the following cost items into the categories of Quality Cost (Prevention, Appraisal, Internal Failures and External Failures). Items that are not quality cost should be grouped into non-quality cost category · Incoming parts inspection · In-process inspection · Quality planning · Final inspection · Unit testing · Design Review · Process capability evaluations · Quality improvement team meetings · Quality education and training · Routine maintenance · Code walkthrough · Supplier...

  • Miller and Sons' static budget for 10,300 units of production includes $35,400 for direct materials, $52,400...

    Miller and Sons' static budget for 10,300 units of production includes $35,400 for direct materials, $52,400 for direct labor, variable utilities of $6,900, and supervisor salaries of $15,700. A flexible budget for 14,000 units of production would show Round your final answer to the nearest dollar. Do not round interim calculations, a. direct materials of $48,117, direct labor of $71,223, utilities of $9,379, and supervisor salaries of $15,700 Ob the same cost structure in total Octotal variable costs of $110,400...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT