According to the manufacturing framework, what is the immediate preceding process that provides input for the...

According to the manufacturing framework, what is the immediate preceding process that provides input for the MPS process? Select one: a. MRP b. S&OP c. Demand Management d. Aggregate Planning

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct option is d. Aggregate Planning as the inputs for MPS are provides by the aggregate planning.

Do give a positive rating if you think this answer helped

Add a comment
Know the answer?
Add Answer to:
According to the manufacturing framework, what is the immediate preceding process that provides input for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT