Match column A with B
Column A |
Column B |
|
___ Input to “develop schedule” |
|
____Business case |
|
____Approving or rejecting change |
|
____Estimate costs |
|
____Project management plan |
|
____Authorizes |
|
___ Subdividing |
|
____Input to “control scope” |
|
____Rolling wave |
|
____Greatest time period |
1. Project manager uses monitoring and controlling process group to review progress and documents benchmarks. Hence we can say that it refers to project management plan. Thus option 5 is correct match for first.
2. In any project project charter, project management are generally refers for the scope so for second option 8 is correct match.
3. Rolling wave planning is kind of technique used in project management which involves elaborate detail of work on ongoing basis. So for third option 9 is correct match.
4.integrates and conslidates refers to the factor where other management teams authorises the project. So for this one option - is correct.
5. WBS refers to work breakdown structure which refers to the subdivision of works into various sections. Thus for fifth option 7 is correct.
6. For creating schedule we have to estimate time taken by each part of work. So for sixth one option 1 is correct.
7. Scope verification is time taking task. So for this one option 9 is correct.
8. Worth the investment deals with the profit and loss which will handle by business team so for eighth one option 2 is correct.
9.Change control board decides which changes needs to be done. So for ninth one option 3 is correct.
*If you have any problem with the answer or want me to edit the answer just let me know in the comments and i will try to get on it as soon as possible. Do give a plus if this answer helps.
Match column A with B Column A Column B 7.1 ___ Input to “develop schedule” Monitoring...
Table 1.1 Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...
Project Description: Student groups will select an industrial project to be developed throughout the semester. Students groups will select an appropriate project and define measurable project objectives and requirements. A project plan and schedule will be generated as well as resources allocated to accomplish project objectives. Prepare a group project for the class. Use as your model one of the following Construction project Software development project Events management project ( e.g. Awards banquet) New product development Project Components: Using the...
Determine the following: -organizationap chart -stakeholder register -charter -scope statement -WBS -Schedule assignment -cost assignment -earned value assignment Problem Case Summary Wilmont's is a top-ranked US retail pharmacy with more than 8,000 stores nationwide. The company is secretly considering delivering prescriptions by flying drone. Drone Tech, a small firm in San Francisco, CA announced the approach in March, and Wilmont's has made an agreement with DroneTech to prototype this project in the San Francisco area. Drone Tech will provide the...
Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...
•Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...
Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...