What cycle time would match capacity and demand if demand is 167
units a day, there are 1 shift(s) of 452 minutes each, and workers
are given three 45 minute breaks during each shift, one of which is
for lunch or dinner? (Round your answer to 2 decimal
places.)
Cycle time
minutes per cycle
Demand = 167 Units / Day
1 shift = 452 minutes
There are three breaks of 45 minutes
Net time available for production = 452 - 45 x 3
= 452 - 135
= 317 minutes
Cycle time = Net time available for production / Units to be produced
= 317 / 167
= 1.90 minutes per cycle
Kindly comment if you need further assistance.
What cycle time would match capacity and demand if demand is 167 units a day, there...
Compute the takt time for a system where the total time per shift is 480 minutes, there are two shifts, and workers on each shift are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 650 units. What cycle time would match capacity and demand if demand is 120 units a day, there are two shifts of 480 minutes each, and workers are given two half-hour breaks during each shift, one of which is for lunch or...
QUESTION 23 3 points Save Answer A small manufacturing company has a daily demand for product at 4000 units/day. The plant operates for 1 shift/day of 480 minutes. Workers have two 15 minute breaks and 30 minute lunch - machines are idle during these breaks. Calculate the Takt Time (cycle time) for this company. TT T Arial 3 (12pt) T-5 E-Seis Path: p Words:0
The work shift at the ABC Company runs fr lunch from 11:30 to 12:15 p.m. that does not count as part of the work shift (workers are not paid for this time). The company provides two 12-minute rest breaks during working hours (paid time), one in the morning and one in the afternoon. The com m. to 4:15 p.m. with a 45 minute break for pany also allows 25 minute day for personal needs (paid time). In addition, a work...
Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 Annual conversion costs: $372,000,000 Actual velocity: 72 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time...
Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units actual run time this week! Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (including defects 4,900 minutes 7.003 minutes 3.8 units per minute 4.0 units per minute 15.827 units 18,620 units Book Required: 1....
Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 5.696 minutes 6,400 minutes 1.68 units per minute 2.00 units per minute 12,670 units 18,100 units Required: 1. Compute...
The plant works one eight hours shift each day. Each day there are two 15-minute breaks and a ove hrour meeting The part has a cycle time of 26 minutes. The customer needs 30 parts per day parts are delivered in a box of 15 parts each. how many people are need for this cell ? 1 2 3 4
1) Following is cost structure of an independent comic book publisher: Fixed cost = 75,000 Variable cost = 8.00 per book Selling price = 13.00 per book Compute the following: How many books have to be sold to make a profit of 2000 dollars? (3 points) The publisher has an estimate of demand of 5000 books. At what selling price would the publisher break even? (6 points) #2) TransCanada Corp. is in the business of manufacturing toys...
Cycle Time, Velocity, Product Costing Mulhall, Inc., has a JIT system in place. Each manufacturing cell is dedicated to the production of a single product or major subassembly. One cell, dedicated to the production of mopeds, has four operations: machining, finishing, assembly, and qualifying (testing). The machining process is automated, using computers. In this process, the model’s frame and engine are constructed. In finishing, the frame is sandblasted, buffed, and painted. In assembly, the frame and engine are assembled. Finally,...
Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipped Actual run time this wook Machine time available per week Actual run note this week Ideal run rate Defect-free output this week Total output this week (including defects) 6,600 minutes 11,000 minutes 5.1 units per minute 6 units per minute 23,562 units 33,660...