Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following in
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1-a. Utilization rate = (Actual Run time this week/Machine time available per week) * 100 = (6,600/11,000) * 100 = 60%

1-b. Efficiency rate = (Actual run rate this week/Ideal run rate) * 100 = (5.1/6) * 100 = 85%

1-c. Quality rate = (Defect - free output this week/ Total output this week (including defects) * 100 = (23,562/33,660) * 100 = 70%

1-d. Overall equipment effectiveness = Utilization * Efficiency * Quality = 60% * 85% * 70% = 35.7%

2-a. Utilization loss in units = (Machine time available per week - Actual run time this week) * Actual run rate this week = (11,000 - 6,600) * 5.1 = 22,440 units

2-b. Efficiency loss in units = (Ideal run rate - Actual run rate this week) * Actual run time this week = (6 - 5.1) * 6,600 = 5,940 units

2-c. Quality loss in units = Total output this week (including defects) - Defect - free output this week = 33,660 - 23,562 = 10,098

Add a comment
Know the answer?
Add Answer to:
Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company...

    00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipood Actual run time this week Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (includine defects 7.500 minutes 12.see minutes 6.30 units per minute 7 units per minute 37,800 units...

  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units actual run time this week! Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (including defects 4,900 minutes 7.003 minutes 3.8 units per minute 4.0 units per minute 15.827 units 18,620 units Book Required: 1....

  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 5.696 minutes 6,400 minutes 1.68 units per minute 2.00 units per minute 12,670 units 18,100 units Required: 1. Compute...

  • Beamer Corporation produces one product and it seems that the demand for that product is exceeding...

    Beamer Corporation produces one product and it seems that the demand for that product is exceeding their manufacturing capacity. Below is the information concerning the machine that produces their product Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 3 3,000 Minutes 5,000 Minutes 3.2 Units per minute 4 Units per minute 7,200 Units 9,600 Units Beamer's overall equipment effectiveness (OEE)...

  • Beamer Corporation produces one product and it seems that the demand for that product is exceeding...

    Beamer Corporation produces one product and it seems that the demand for that product is exceeding their manufacturing capacity. Below is the information concerning the machine that produces their product Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) Beamer's overall equipment effectiveness (OEE) was approximately 3,000 Minutes 5, eee Minutes 3.2 Units per minute 4 Units per minute 7,200 Units...

  • Part I A full shift of production was scheduled to run on machine X. Production was stopped for 2...

    just #3 Part I A full shift of production was scheduled to run on machine X. Production was stopped for 20 minutes due to a machine failure, 10 minutes for a bin change, 30 minutes for a quality concern requiring a tool repair. Assumptions: A) A day- 8 hours with 20 minutes break time B) A total of 1200 parts is processed per day and only 6 is rejected/scraped C)- The ideal cycle time established by engineering or the equipment...

  • A manufacturing company that has only one product has established the following standards for its variable...

    A manufacturing company that has only one product has established the following standards for its variable manufacturing overhead. The company bases its variable manufacturing overhead standards on direct labor-hours. Standard hours per unit of output 5.00 DLHs Standard variable overhead rate $ 11.63 per DLH The following data pertain to operations for the last month: Actual direct labor-hours 8,500 DLHs Actual total variable manufacturing overhead cost $ 95,970 Actual output 1,600 units What is the variable overhead efficiency variance for...

  • Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equ...

    Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equipment a typical Assembly plant for Availability Assumptions: At a typical plant, the constraint in the Widget production process is the machining line. The following information applies to the line for the week of June 5 through June 11. The line was schedulėd to run two &-bour shifts Monday through Friday, and one 9-hour shift on...

  • ses/54538/quizzes/370391/take Question 42 1 pts A manufacturing company that has only one product has established the...

    ses/54538/quizzes/370391/take Question 42 1 pts A manufacturing company that has only one product has established the following standards for its variable manufacturing overhead. Variable manufacturing overhead standards are based on machine-hours. Standard hours per unit of output tandard variable overhead rate 8.1 machine-hours $14.30 per machine-hour The following data pertain to operations for the last month: Actual hours Actual total variable manufacturing overhead cost Actual output 1.700 machine-hours $24.905 200 units What is the variable overhead efficiency variance for the...

  • OVERALL EQUIPMENT EFFICIENCY A CNC machine tool is used for single shift working, the machine tool...

    OVERALL EQUIPMENT EFFICIENCY A CNC machine tool is used for single shift working, the machine tool is operated for 8 hours per shift for 5 days per week. The CNC machine fool produces terminal blocks at a planned production rate of 60 units per hour Using the Availability, Performance and Quality losses given in the table below, (all values are in minutes per week) Calculate the average Overall Equipment Efficiency (OEE) for the machine tool over the three week period...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT