Question

What are the steps to find Gross Requirements for lot for lot ordering MRP schedule? Show...

What are the steps to find Gross Requirements for lot for lot ordering MRP schedule? Show give an example

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Gross requirements for End item is determined based on the Master production schedule. The first step is preparation of demand forecast for the end item. Then the actual customers orders are documented. Based on demand forecast and actual customer orders, Master production schedule (MPS) is prepared. For example, MPS for an end item based on lot-for-lot ordering is as follows:

Week 0 1 2 3 4 5 6
Forecast 350 450 450 450 600 600
Customer Orders (CO) 150 350 500 600 240 200
Projected On Hand inventory 0 0 0 0 0 0 0
MPS quantity 350 450 500 600 600 600
Available-to-promise (ATP) 200 100 0 0 360 400

Following formulas are used in preparing MPS:

On-hand Inventory = Previous on hand inventory - MAX(Forecast, Customer Order)

ATP for week 1 = On hand inventory + MPS in week 1 - Cumulative Customer Orders before the next MPS receipt

ATP for subsequent weeks = MPS of the week - Cumulative Customer Orders before the next MPS receipt

Once, the MPS is prepared, the MPS quantity becomes the Gross requirement for the end item.

The gross requirement for the child item is based on the planned order release of the end item.

For example, if each unit of the end item X requires 2 units of a child item A. On-hand inventory of X is 800 units and that of A is 0. There are no scheduled receipts. And lead time for both items is 1 week.

Then resulting MRP of item X and A are following:

Item 0 1 2 3 4 5 6
X Gross Requirement 350 450 500 600 600 600
SOR = 0 Scheduled Receipt 0 0 0 0 0 0
ss = 0 Projected on Hand 800 450 0 0 0 0 0
Net Requirement 0 0 500 600 600 600
L = 1 Planned Order Receipt 0 0 500 600 600 600
Q = L4L Planned Order Release X 0 500 600 600 600 0
Item 0 1 2 3 4 5 6
A Gross Requirement 0 1000 1200 1200 1200 0
SOR = 0 Scheduled Receipt 0 0 0 0 0 0
ss = 0 Projected on Hand 0 0 0 0 0 0 0
Net Requirement 0 1000 1200 1200 1200 0
L = 1 Planned Order Receipt 0 1000 1200 1200 1200 0
Q = L4L Planned Order Release A 1000 1200 1200 1200 0 0

Following formulas is used to prepare the MRP

Gross Requirements (GR): The total expected demand for an item or raw material during each time period without regard to the amotmt on hand. (For end items it is MPS; for components, these quantifies are derived from the planned-order releases of their immediate "parents."
Scheduled receipts (SR): Open orders that have been placed and are scheduled to arrive from vendors or elsewhere in the pipeline by the beginning of a period.
Projected on hand (POH): Expected inventory available on hand the beginning of each time period.
Net requirements (NR): The actual amount needed in each time period.
Planned-order receipts (PORT): The quantity expected to be received by the beginning of the period in which it is shown.
Planned-order releases (PORL): Equals planned-order receipts offset by lead time. This amount generates gross requirements at the next level in the assembly or production chain. When an order is executed, it is removed from "planned-order releases" and enter under "scheduled receipts"

Gross requirement of item A is equal to the planned order release of item X multiplied by 2   (because 2 units of A are required to make one unit of X)

Add a comment
Know the answer?
Add Answer to:
What are the steps to find Gross Requirements for lot for lot ordering MRP schedule? Show...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT