Question

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $12. There is a carrying cost of $0.015 per unit per week. Beginning inventory is 80 units. WEEK Gross requirerments 25 45 10 20 70 TO 2050 195 TO Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first order released with each method and which periods requirements will be covered by that order. Ordered Loast total cost Least unit cost Periods Covered (Click to select) (Click to select)

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • The following is a partial MRP table. Based on the information provided, an inventory holding cost...

    The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...

  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • The gross requirements for item A are specified for weeks 1 through 12 in the table...

    The gross requirements for item A are specified for weeks 1 through 12 in the table that follows Item A, Level 0 00 01 02 03 04 0506 07 08 09 10 11 12 Gross requirements 0 60 0 50 0 700 400 60 0 50 Planned order release???????????? The lead time is 2 weeks: current on hand inventory, at the beginning of week 1 is 60 units: the order cost is $120 per order, and, the inventory cost s...

  • Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion -...

    Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion - Brunswick Motors," at the end of Chapter 21 in the textbook. Answer Questions 1-3. Given Spread Sheet: A-Topic 3 Part 1&2 AND  A-Topic 3 Part 3 Please use given information, show formulas/ calculations, and give reasons behind answer. Part 2 Gear Box Given Information Setu Invento Number of orders (count cells with values for planned order release Set-up Costs=# of Orders X Setup Costs 8...

  • 1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 ...

    1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 2) E(3 C(2 Requirements include 125 units (80 firm orders and 45 forecast)。亿in week 10 plus the follo wing spares 10 23 17 20 25 Develop the MRP table for this problem. 2) Consider the dynamic demand of an end item following the MRP explosion ess. Time Demand 50 30 20 80 100 The order cost (setup) per order is S125. Inventory carrying...

  • 2) Consider the dynamic demand of an end item following the MRP explosion proces3. Time Demand 50...

    2) Consider the dynamic demand of an end item following the MRP explosion proces3. Time Demand 50 75 The order cost (setup) per order is S125. Inventory carrying charge is assumed to be $1 per unit per time period. Find out the dynamic lot sizes for this problem by using a) Silver-Meal Method b) LUC method c) PPB method d) Solve the problem optimally by using the Wagner Within algorithm e) Compare and contrast the total cost of the obtained...

  • Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...

  • Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing​ (PPB) solution and calculate the total relevant costs for the plan.        Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 60 20 10 80 40 ​Also, for this plan the Holding cost =​$2.50​/unit/week;...

  • Table below is a time-phased net requirements for Widgets over the next six weeks along with...

    Table below is a time-phased net requirements for Widgets over the next six weeks along with the capacity constraint. Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 Capacity 600 600 600 400 200 200 The setup cost is $200 and the holding cost is $0.30 per unit per week. Accounting for the capacity constraint, the modified requirements schedule, with improvement step, is: Note: Enter your answer as integer. Week Requirement, y (Hint: You want...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT