Question

2) Consider the dynamic demand of an end item following the MRP explosion proces3. Time Demand 50 75 The order cost (setup) p

0 0
Add a comment Improve this question Transcribed image text
Answer #1


MRP Explosion a) Silver-Meal Method A $125, h $1/unit/ period m-1K(1) : 125 m 2 K (2) (1/2)*(125+ (1)*75) 100 < K (1) so cont

c) PPB method ppF A/h 125 From period 1 PP1-0 PP2 75<125 PP3 75+ (2)30 135 > PPF, STOP Q1 50 75 125 units From period 3 PP1-0

d) Solve the problem optimally by using the Wagner Within algorithm? Cij sum of production & inventory costs required to sati

Add a comment
Know the answer?
Add Answer to:
2) Consider the dynamic demand of an end item following the MRP explosion proces3. Time Demand 50...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 ...

    1. Consider the necessary information for an MRP application provided On hand Lead Time 24 32 80 2) E(3 C(2 Requirements include 125 units (80 firm orders and 45 forecast)。亿in week 10 plus the follo wing spares 10 23 17 20 25 Develop the MRP table for this problem. 2) Consider the dynamic demand of an end item following the MRP explosion ess. Time Demand 50 30 20 80 100 The order cost (setup) per order is S125. Inventory carrying...

  • The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...

    The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $12. There is a carrying cost of $0.015 per unit per week. Beginning inventory is 80 units. WEEK Gross requirerments 25 45 10 20 70 TO 2050 195 TO Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first order released with each...

  • Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion -...

    Refer to the Excel speadsheet, "Inventory Management," to complete the "Analytics Exercise: An MRP Explosion - Brunswick Motors," at the end of Chapter 21 in the textbook. Answer Questions 1-3. Given Spread Sheet: A-Topic 3 Part 1&2 AND  A-Topic 3 Part 3 Please use given information, show formulas/ calculations, and give reasons behind answer. Part 2 Gear Box Given Information Setu Invento Number of orders (count cells with values for planned order release Set-up Costs=# of Orders X Setup Costs 8...

  • Demand for an item is forecasted at 100, 150, 75, 75, 50, and 60. Each setup...

    Demand for an item is forecasted at 100, 150, 75, 75, 50, and 60. Each setup costs $80, and inventory holding cost is $1.25 per week. Find the order quantities selected by the Silver-Meal heuristic.

  • please make sure the answer is correct 100% Exercise 2: The time phased net requirements for...

    please make sure the answer is correct 100% Exercise 2: The time phased net requirements for the base assembly are given as follows. Setup cost is $300, and the holding cost is $0.50 per assembly per week. Week 2 3 4 5 6 Req 250 150 140 400 200 200 a. Determine the lot sizes using Silver Meal heuristic. b. Determine the lot size using least unit cost heuristic.

  • The following is a partial MRP table. Based on the information provided, an inventory holding cost...

    The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...

  • Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42...

    Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42 84 86 7 18 49 30 End item A has a planned lead time of two weeks. There are currently 120 units on hand and no scheduled receipts. a. Compute the planned order releases using lot-for-lot b. Compute the planned order releases using part-period balancing where the ratio of the setup cost to the holding cost is 200 c. Compute the planned order releases...

  • Consider the following information about an end-product item: Ordering cost =$45/order Average usage =12 units/week Inventory...

    Consider the following information about an end-product item: Ordering cost =$45/order Average usage =12 units/week Inventory carrying cost =$1/unit/week (a) How many orders should we place per year (52 weeks) to replenish inventory of the item based on average weekly demand? (b) Given the following time-phased net requirements from an MRP record for this item, determine the sequence of planned orders using economic order quantity (EOQ) and periodic order quantity (POQ) procedures. Assume lead time equals zero and current on-hand...

  • Juicy & Fresh U&F) produces and bottles fruit juices in different flavors and container sizes.J&F is implem...

    Juicy & Fresh U&F) produces and bottles fruit juices in different flavors and container sizes.J&F is implementing a new Advanced Planning System APS) to manage its production planning. The new system provides flexibility in the selection of the lot-sizing method to be used in the MRP calculations. The APS offers a set of different standard lot-sizing methods and the possibility to use a customized method. The company's manager is not sure about which lot-sizing method would benefit most to J&F....

  • Value Gadgets Corp. produces​ J-Pods, music players that can download thousands of songs. Value G...

    Value Gadgets Corp. produces​ J-Pods, music players that can download thousands of songs. Value Gadgets forecasts that demand in 2017 will be 19,500 ​J-Pods. The variable production cost of each​ J-Pod is $50. In its MRP ​system, due to the large $22,750 cost per​ setup, Value Gadgets plans to produce​ J-Pods once a month in batches of 1,625 each. The carrying cost of a unit in inventory is $21 per year. Question: 1. Using the MRP​ system, what is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT