Question

Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $3,000. It seems

Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a.What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

a.
Total Plant Manufacturing overhead = $852,600
Total Plant Direct Labor Cost = $609,000

Overhead rate = 852,600 X 609,000 = $1.4 per labor cost dollar

b.
Rate = $1.4
Total Labor Cost in Koopers job = $10,400
Overhead cost = 10,400 X 1.4 = $14,560

2.

Fabricating Machining Assembly Total
Manufacturing Overhead A $        3,55,250 $        4,06,000 $            91,350 $        8,52,600
Direct labor B $        2,03,000 $        1,01,500 $        3,04,500 $        6,09,000
Rate A / B $                1.75 $                4.00 $                0.30
Fabricating Machining Assembly Total
Direct Material $              3,300 $                  200 $              1,700 $              5,200
Direct labor $              3,400 $                  500 $              6,500 $            10,400
Overhead $              5,950 $              2,000 $              1,950 $              9,900
(1.75 X 3,400) (4 X 500) (0.3 X 6,500) $            25,500

4.

Fabricating Machining Assembly Total
Direct Material $            3,300 $          200 $          1,700 $        5,200
Direct labor $            3,400 $          500 $          6,500 $     10,400
Overhead $            4,760 $          700 $          9,100 $     14,560
(1.4 X 3,400) (1.4 X 500) (1.4 X 6,500) $     30,160
BID Price 30,160 X 1.5 $ 45,240.0
Fabricating Machining Assembly Total
Direct Material $              3,300 $                  200 $              1,700 $              5,200
Direct labor $              3,400 $                  500 $              6,500 $            10,400
Overhead $              5,950 $              2,000 $              1,950 $              9,900
(1.75 X 3,400) (4 X 500) (0.3 X 6,500) $            25,500
BID Price 25,500 X 1.5 $        38,250.0
Add a comment
Know the answer?
Add Answer to:
Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to th...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • 3. Award: 30.00 points “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost...

    3. Award: 30.00 points “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to...

  • “Blast it!" said David Wilson, president of Teledex Company. “We've just lost the bid on the...

    “Blast it!" said David Wilson, president of Teledex Company. “We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures produ

    “Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT