Question

Problems 1. Alima runs a specialty sewing shop in Abu Dhati and doss repairs and siteration on mens and womens clothing. Fo
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

Wages(A) = 16,000 dirhams
Other employment benefit payments(B) = 4,000 dirhams

Total Labour Cost= (A+B) = 16,000 + 4,000 = 20,000 dirhams

Total labour hours for the month = 500 hours

Labour Cost per hour (excluding profit margin) = 20,000/500 = 40 dirhams per hour

Profit margin to account for owner's effort = 22 dirhams per labour hour

Labour cost per hour (including profit margin) = 40 + 22 = 62 dirhams per hour

b.

Total hours required for the big job = 200 hours

Materials cost = 12,000 dirhams

Total Bill is as follows

Rate Cost
Materials 12,000
Labor Charges 40 8,000
Material loading 30% of material 3600
Overhead 8 1,600
Total Cost 25,200
Profit Margin 22 4,400
Total 29,600
Add a comment
Know the answer?
Add Answer to:
Problems 1. Alima runs a specialty sewing shop in Abu Dhati and doss repairs and siteration on men's and women's clothing. For some reason, she uses ime and material priing techniques to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problems 1. Alima runs a specialty sewing shop in Abu Dhati and doss repairs and siteration...

    Problems 1. Alima runs a specialty sewing shop in Abu Dhati and doss repairs and siteration on men's and women's clothing. For some reason, she uses ime and material priing techniques to determine prices to charge customers For May 2019, she estimates that wages will be 16,000 dirhams, other employment benets payments will be 4,000 dirhams and overhead will be 4,000 dirhams. She estimates that her employees will work 500 hours in May She applies a proft margin of 22...

  • WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours)...

    WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges Material Loading Charges Labor wages (5,700 hours) $238,260 Supervisor’s salary $62,000 Clerical and accountant wages 58,140 4,000 Irrigation supplies manager 39,000 Overhead 53,010 21,720    Total $349,410 $126,720 Waterways has budgeted for 5,700 labor hours. It desires a $13 profit margin per hour of labor and 15% profit on materials. It estimates the total invoice cost of materials in the coming year will be $660,000. A.Compute the rate per hour of labor....

  • Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the...

    Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Time Charges $243,000 Material Loading charges Labor wages (6,000 hours) Supervisor's salary Clerical and accountant wages Irrigation supplies manager Overhead 58,800 $57,000 3,000 41,000 21,140 $122, 140 57,000 $358,800 Total Waterways has budgeted for 6,000 labor hours. It desires a $15 profit margin per hour of labor and 16% profit on materials....

  • P22-3B Armstrong Bike Repair Shop has budgeted the following time and material for 2017 Armstrong Bike...

    P22-3B Armstrong Bike Repair Shop has budgeted the following time and material for 2017 Armstrong Bike Repair Shop Budgeted Costs for the Year 2017 Time Material Charges Loading Charges Shop employees' wages and benefits $36.000 Parts supervisor's salary and benefits $20,000 Office employee's salary and benefits 15,000 10,000 Overhead (supplies, depreciation, advertising, utilities) 19,000 15,000 Total budgeted costs $70.000 $45.000 Armstrong budgets 2,500 hours of repair time in 2017 and will bill a profit of $5 per labor hour along...

  • Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigatio...

    Question 9 View Policies Current Attempt in Progress Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows. WATERWAYS CORPORATION Budgeted Costs for Irrigation Projects Material Time Loading Charges Charges Labor wages (5900 hours) $237770 Supervisor's salary $61000 Clerical and accountant wages 63130 4000 Irrigation supplies manager 41000 Overhead 54280 22050 Total $355180 $128050 Waterways has budgeted for 5900 labor hours. It desires a $13 profit margin per hour...

  • Betty runs a shop where she sells $1 each cookie. In a year, she could sell...

    Betty runs a shop where she sells $1 each cookie. In a year, she could sell 200,000 cookies average. She employs 5 people who each worked a total of 500 hours a year. She paid them a wage of $10 per hour. She also has costs from equipment and raw materials around $75,000 a year. Other companies have offered to pay Betty $80,000 if she would come to work for them. She could rent out her shop for $5,000; assume...

  • Practice Problem 1 Sutton's Electronic Repair Shop has budgeted the following time and material for 2020....

    Practice Problem 1 Sutton's Electronic Repair Shop has budgeted the following time and material for 2020. SUTTON'S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Time Charges Material Loading Charges Shop employees' wages and benefits $101,050 Parts manager's salary and benefits $25,400 Office employee's salary and benefits 20,210 17,650 Overhead (supplies, depreciation, advertising, utilities) 24,440 16,800 Total budgeted costs $145,700 $59,850 Sutton's budgets 4,700 hours of repair time in 2020 and will bill a profit of $14 per labor...

  • Presented below are data relating to labor for Verde Appliance Repair Shop. Repair-technicians' wages Fringe benefits...

    Presented below are data relating to labor for Verde Appliance Repair Shop. Repair-technicians' wages Fringe benefits Overhead $80,000 20,000 40,000 The desired profit margin per hour is $15.00. The material loading charge is 60% of invoice cost. Verde estimates that 4,000 labor hours will be worked next year. If Verde repairs a dishwasher that takes 1.2 hours to repair and uses parts of $60.00, compute the bill for the job. (Round answer to 2 decimal places, e.g. 10.50.) hours to...

  • Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020....

    Practice Problem 1 Sutton’s Electronic Repair Shop has budgeted the following time and material for 2020. SUTTON’S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Time Charges Material Loading Charges Shop employees’ wages and benefits $99,640 ― Parts manager’s salary and benefits ― $25,400 Office employee’s salary and benefits 17,860 13,360 Overhead (supplies, depreciation, advertising, utilities) 28,200 19,380 Total budgeted costs $145,700 $58,140 Sutton’s budgets 4,700 hours of repair time in 2020 and will bill a profit of $14...

  • Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR...

    Sutton's Electronic Repair Shop has budgeted the followingg time and material for 2020. SUTTON'S ELECTRONIC REPAIR SHOP Budgeted Costs for the Year 2020 Material Loading Charges Time Charges $118,800 Shop employees' wages and benefits Parts manager's salary and benefits $25,400 21,600 15,400 Office employee's salary and benefits 27,000 17,340 Overhead (supplies, depreciation, advertising, utilities) $167,400 $58,140 Total budgeted costs Sutton's budgets 5,400 hours of repair time in 2020 and will bill a profit of $14 per labor hour along with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT