B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process asse

0 0
Add a comment Improve this question Transcribed image text
Answer #1

192. In performing qualitative risk analysis process, the organization's risk tolerance associated with the project constraints of cost , schedule, scope and quality is not considered. Hence, option D is the right.

193. Work breakdown structure is not an output of the Monitor risk process. It is a project deliverable. Hence, option A is the right choice.

194. It is not a technique that identifies strength and weakness of the organisation regardless of the project or general business area as it is very strategic in nature, hence it is very specific for each type of business. Hence, option B is the right choice.

195. Expert judgement is a tool and technique for this process not an input of implement risk response process. Hence, option D is the right choice.

Add a comment
Know the answer?
Add Answer to:
B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all af the following EXCEPT A....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT