QUESTION 42 The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the followin

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer is A mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy

All other options are used by Qualitative risk analysis process

Add a comment
Know the answer?
Add Answer to:
QUESTION 42 The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the following EXCEPT O Relative probability or likelihood of occurrence of identified...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT