MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minu...

MCE

Craig, Inc., has provided the following information for one of its products for each hour of production:

Actual velocity: 100 units (per hour)
Move time: 18 minutes
Inspection time: 13 minutes
Rework time: 15 minutes

Required:

1. Calculate MCE. If required, round your answer to two decimal places.

2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places.

Theoretical cycle time minutes
Actual cycle time minutes
MCE

3. What if waste is reduced by 30 percent?
New waste =  minutes

What is the new MCE? If required, round your answer to two decimal places.

What is the new cycle time?
minutes

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

1.

Process time          = Total time – Move time – Inspection time – Rework time

Process time = 60 minutes – 18 minutes – 13 minutes – 15 minutes = 14 minutes

MCE = Process time /(Process time + Move time + Inspection time + Rework time)

MCE = 14/(14+18+13+15) = 0.233

2.

Theoretical cycle time = Process time / Number of units in an hour = 14 minutes/100 units = 0.14 minute

Actual cycle time = Total time/Number of units = 60 minutes/100 units = 0.60 minutes

MCE = Theoretical cycle time/Actual cycle time = 0.14/0.60 = 0.233

3.    

New waste = (1-0.30)(18 minutes + 13 minutes + 15 minutes) = 32.2 minutes

       

New MCE = 14/(14 + 32.2) = 0.30

New cycle time = (14+32.2)/100 = 0.462 minutes

----------------------------------------------------------------------------------------------------

***************THANK YOU*****************

Add a comment
Know the answer?
Add Answer to:
MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minu...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MCE Craig, Inc., has provided the following information for one of its products for each hour...

    MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 10 minutes Inspection time: 15 minutes Rework time: 12 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time...

  • MCE Craig, Inc., has provided the following information for one of its products for each hour...

    MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 12 minutes Inspection time: 12 minutes Rework time: 10 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time...

  • Craig, Inc., has provided the following information for one of its products for each hour of...

    Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 20 minutes Inspection time: 14 minutes Rework time: 13 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time minutes...

  • Craig, Inc., has provided the following information for one of its products for each hour of...

    Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 20 minutes Inspection time: 12 minutes Rework time: 12 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time minutes...

  • Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the...

    Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 180,750 laptops per quarter but currently produces 72,300 units. The conversion cost per quarter is $7,230,000. There are 60,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 9 minutes of move time, 19 minutes of wait time, and 5 minutes of rework time. (All work...

  • Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the...

    Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 193,500 laptops per quarter but currently produces 77,400 units. The conversion cost per quarter is $9,288,000. There are 64,500 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 11 minutes of move time, 19 minutes of wait time, and 6 minutes of rework time. (All work...

  • Cycle Time and velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to...

    Cycle Time and velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 260,000 laptops per quarter but currently produces 78,000 units. The conversion cost per quarter is $8,190,000. There are 65,000 produ the processing minutes per unit used, the production of the laptops uses 9 minutes of move time, 21 minutes of wait time, and 6 minutes of rework time. (All work is done by cell workers.) Required: 1. Compute the theoretical...

  • Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 A...

    Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 Annual conversion costs: $372,000,000 Actual velocity: 72 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time...

  • Cycle Time, Velocity, Product Costing Mulhall, Inc., has a JIT system in place. Each manufacturing cell...

    Cycle Time, Velocity, Product Costing Mulhall, Inc., has a JIT system in place. Each manufacturing cell is dedicated to the production of a single product or major subassembly. One cell, dedicated to the production of mopeds, has four operations: machining, finishing, assembly, and qualifying (testing). The machining process is automated, using computers. In this process, the model’s frame and engine are constructed. In finishing, the frame is sandblasted, buffed, and painted. In assembly, the frame and engine are assembled. Finally,...

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT