Question

Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days
Required: 1. Compute the throughput time. (Round your answer to 1 decin 2. Compute the manufacturing cycle efficiency (MCE) f
newconnect.mheducatio Email - Georgia Southern University omework i Saved Inspection time Wait time (from order to start of p
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: 1) Through put Time = process time + Inspection Time + move time = 3.2 days to.5 daw + Quelle time = 3.2 days +0.5 da

Add a comment
Know the answer?
Add Answer to:
Check my w Inspection time Wait time (from order to start of production) Process time Move...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between w...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.3 days 16.7 days 3.0 days 1.1 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.5 days Process time 3.1 days Move time 1.1 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.6 days 16.5 days 2.7 days 1.3 days 4.1 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 16.4 days 3.0 days 0.7 days 3.7 days Required: 1. Compute the throughput time. (Round your answer to...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) 0.4 days 16.0 days 2.9 days 0.6 days 3.6 days Process time Move time Queue time Required: 1. Compute the throughput time. (Round your answer to...

  • Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln,...

    Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.7 days 15.2 days 3.2 days 0.7 days 4.0 days Required:...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer pla...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time 0.2 days 16.2 days 3.2 days 1.4 days 4.1 days 09 Move time Queue time Required: 1. Compute the throughput time. (Round your answer...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order tostart of production) Process time Move time 0.2 day 17.0 days 3.2 days 0.5 day 3.7 days Queue time Required: 1.Compute the throughput time. (Round your answer to 1 decimal...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: 0.3 days Inspection time Wait time (from order to start of production) Process time Move time Queue time 15.6 days 2.6 days 0.6 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT