Fundamentals of Engineering Question - 20 points
Reference Figure "EE". Your survey crew has provided you with the following coordinates for the tract of land shown in this Figure "EE".
Point A X1 = 100' Y1 = 100'
Point B X2 = 223' Y2 = 528'
Point C X3 = 457' Y3 = 666'
Point D X4 = 630' Y4 = 323'
Point E X5 = 365' Y5 = 198'
You are in charge of ordering the dirt for adding 2'4" ( 28") of elevation to the entire tract of land.
The dirt will need to be compacted and it has a compaction percentage of 9.5%
How much dirt will you need to order to make this compacted fill on the whole piece of property.
Fundamentals of Engineering Question - 20 points Reference Figure "EE". Your survey crew has provided you with the following coordinates for the tract of land shown in this Figure "EE"...