Question

(4). (8 pts). A soil profile is shown in below Figure. A uniformly distributed load Ao is applied at the surface of soil. Giv
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ho=5m; eo=Gw=2.75x.38=1.045

sat/clay(sat)ctay (2.751.045) x 9.8/(1 +1.045) 18.18kN/m

σ = σ一u = 12 × 2 + 18 × 3 + 18.18 × 2.5-(3+2.5) × 9.8 = 69.55kN/m

\bar{\sigma}+\Delta\sigma=69.55+60=129.55 kN/m^2

So soil is pre-consolidated from 69.55 kN/m^2 to 92.6 kN/m^2 and normally consolidated from 92.6 kN/m^2 to 129.55 kN/m^2

To find Liquid limit-

(wi-w2) /log10(N2/M) = (wi-w L)/ log10(25/N1)

(42.2ー39.1)/logo(28/15) = (42.2-wL)/logo(25/ 15)

W1 = 39.66W1 = 39.66%

Cc = 0.009 × (WL-10)

Cc = 0.009 × (39.66-10)

C_c=0.267

C_r=C_c/6=0.267/6=0.0445

a). Consolidation Settlement-

\Delta H=C_r H_olog_1_0(\sigma_c/\bar{\sigma_0})/(1+e_o)+C_c H_olog_1_0(\bar{\sigma_0}+\Delta\sigma)/\sigma_c//(1+e_o)

0.0445x 5x logo(92.6/69.55)/(1+1.045)+0.267x 5x logo(129.55/92.6)/(1+ ΔΗ 1.045)

\Delta H=0.0135+0.0952 = 0.1087m=108.7mm

b). Time to consolidate  

(T_v)_9_8=1.781-0.9332 log_1_0(100-98)=1.5

(T_v)_9_8=c_v\times t_9_8/d^2

t98-1.5 × 5002/0.002= 5.95years

Add a comment
Know the answer?
Add Answer to:
(4). (8 pts). A soil profile is shown in below Figure. A uniformly distributed load Ao is applied at the surface of soil. Given the preconsolidation pressure is between swell index and compressio...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2. [2596] Figure 2 shows a soil profile. The uniformly distributed load on the ground...

    Problem 2. [2596] Figure 2 shows a soil profile. The uniformly distributed load on the ground surface is (1) Estimate the primary consolidation settlement of the clay layer due to the application of Ap. (2) If the clay layer is preconsolidated and the average preconsolidation pressure is 80 kPa, what will be the expected primary consolidation settlement if the recompression index is C 0.2 x Cc? p 87 kPa 1 m Dry Sand Sand: Saturated Sand Dry Unit weight: 14.6...

  • 3. A soil profile shown below. The uniformly distributed load on the ground surface is Do....

    3. A soil profile shown below. The uniformly distributed load on the ground surface is Do. Estimate the primary settlement of the normally consolidated clay layer, given that H-6ft, H2 - 10 ft, Hz - 4ft For sand, Ydry = 113 lb/ft'Ysat = 188.7 lb/ft? For clay, Ysat - 186.4 lb/ft. e=0.85, LL = 55 Ao'-2,000 lb/ft? -0.0003 in /sec 140' Dry sand Satiiruted sand Primary Settlement, Sc of Normally Consolidated clay - If the clay above was overconsolidated, what...

  • TO. A uniformly distributed surcharge of T50 kN/m2 was applied at the ground surface of the...

    TO. A uniformly distributed surcharge of T50 kN/m2 was applied at the ground surface of the soil profile shown below. Based on the consolidation laboratory ratio is 0.8, compression index is 0.45 and swell index is 0.1, det (30 points) results, the initial void ermine the following: A) Effective stress and pore water pressure at the mid-depth of layer 4. B) Primary consolidation settlement if the clay layer is normally consolidated. C) Primary consolidation settlement if the precompression pressure i5...

  • Two undisturbed clay samples were taken from the middle of the overconsolidated and normally consolidated clay layers in the soil profile shown. The water table is at the top of the overconsolidated c...

    Two undisturbed clay samples were taken from the middle of the overconsolidated and normally consolidated clay layers in the soil profile shown. The water table is at the top of the overconsolidated clay layer. Consolidation tests were carried out on the two samples and the results are summarized in the table below. Assume that the bulk, dry, and saturated unit weights of the sand are 16 kN/m3, 16 kN/m3 and 19 kN/m3, respectively. The specific gravity of the clay soil...

  • In the figure below, the natural soil profile consists of sand overlying clay overlying sand overlying bedrock. A water...

    In the figure below, the natural soil profile consists of sand overlying clay overlying sand overlying bedrock. A water table is present 1 m beneath the surface of the natural ground. If 4 m of consistent fill material (γfill = 15 kN/m3) was placed on top of this soil profile that covered a large area, determine: (a) The consolidation settlement of the clay layer (using 4 equal layers in your calculation), and (b) The time (in days) for this consolidation...

  • Question 5 (20 marks) A I-m thick, c applied on the top surface of the clay using Sheepsfoot rollers t Ily-saturate...

    Question 5 (20 marks) A I-m thick, c applied on the top surface of the clay using Sheepsfoot rollers t Ily-saturated clay is resting on a dry sand when a uniform load of 200 kN/m2 is expedite consolidation process For the saturated clay layer, the initial void ratio of 5.0, specific gravity of 2.65, pre-consolidation ression index of 0.2, and the stress of 20 kN/m2: the compression index of 0.5, the recomp coefficient of consolidation of 0.001 cm2 s" a)...

  • 4. (10 pts) The soil profiles at a site is as follows (from the ground surface down); 5 m of very...

    4. (10 pts) The soil profiles at a site is as follows (from the ground surface down); 5 m of very dense, saturated sand (saturated unit weight- 19.5 kN/m) 8 m of normally consolidated clay ( 7.5 kN/m, Ce-0.5) 15 m of clay (7'-80 kNan', σ'p-250 kN/m. (σ'max), Ce-0.4, Cer : 0.04). A layer of fill, 15m deep (y = 19 kN/m) will be added to the top of this profile. The water table is originally at the ground surface-...

  • The ground profile of a construction site consists of a 3 m thick layer of sand...

    The ground profile of a construction site consists of a 3 m thick layer of sand followed by a 2 m thick layer of clay lying on impervious bedrock. The watertable is at a depth of 2 m below the ground surface. The sand has a dry unit weight of 16 kN/m and a saturated unit weight of 18 kN/m3. The capillary rise in sand is 0.5 m. The clay has a bulk unit weight of 19 kN/m 1. One...

  • e3 shows the soil profile (sand-clay-sand) at the site of a warehouse that causes a surface...

    e3 shows the soil profile (sand-clay-sand) at the site of a warehouse that causes a surface ding of 100 kPa. (pw= 1000 kg/m; g 9.81 m/s2) on 4 (25 marks) A clay sample was cored at 7 m depth (middle of the clay layer). Based on laboratory test data, it was found that the clay was over-consolidated with OCR = 2.5 (before applying surface loading), compression index Ce 0.44 and recompression index C. = 0.1. The consolidation coefficient of clay...

  • Question 2 [Marks: 15 +10=25] 200kPa of construction stress was applied on top of the soil...

    Question 2 [Marks: 15 +10=25] 200kPa of construction stress was applied on top of the soil layers as shown in the figure below. (1) Calculate the settlement in the clay layer due to the construction (minimum of 2 sub layers is to be used). (W) If the soil went through 90% average degree of consolidation in 1 year, calculate the coefficient of consolidation (C.). 个 Sand Y = 20kN/m 4m Water table Clay (over consolidated) y = 16kN/m 100 4m...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT