Question 1)
a) Calculation of IRR
IRR is the rate at which all the present value cash inflows are equal to the present value of cash outflows.
There is one cash inflow of $9 million now and two cash flows of $6 million each in the upcoming two years.
You can simply input (-9,000,000) in Year 0's cash flow. The minus sign signifies a cash outflow. Then input 6,000,000 in Year 1 and Year 2. Then using your financial calculator, compute IRR. The result will be 21.5250437% or 21.53%.
If you are having difficulties using your financial calculator, you can solve for i% in the following formula by iteration:
Present Value of Cash Inflows = Present Value of Cash Outflows at i%
or, 9,000,000 = 6,000,000/(1+i%) + 6,000,000/(1+i)^2
Following this method will also yield you the same result of IRR of 21.53%.
Calculation of NPV
NPV is the Present Value of cash inflows net of present value of cash outflows.
You can either using the same steps as IRR to compute NPV in your financial calculator after inputting the interest rate at 10%. You can simply input (-9,000,000) in Year 0's cash flow, then input 6,000,000 in Year 1 and Year 2. Using a discount rate of 10% in your financial calculator, compute NPV. The answer will be $1,413,223.141.
If you have difficulty doing so, calculate NPV using its formula:
NPV = Present Value of cash Inflows - Present Value of cash Outflows at the given discount rate
Using the above formula, we calculate NPV as:
YEAR | CASH FLOW | Formula for Present Value | Present Value |
0 | -$9 million | -$9 million/(10%)^0 | -$9 million |
1 | $6 million | $6 million/(1+10%)^1 | $5,454,545.455 |
2 | $6 million | $6 million/(1+10%)^2 | $4,958,677.686 |
Total Present Value | $1,413,223.141 |
Using the above method or your financial calculator will yield the same result of $1,413,223.141.
Conclusion
Since, the Net Present Value is positive, we accept the project. The IRR (21.53%) is greater than the cost of capital (10%) and so the IRR criteria permits acceptance of the project. Therefore, at 10% level of discount, both NPV and IRR rules agree.
b) The NPV rule states that if there are multiple contracts, we always choose the one with the highest NPV. Since, different combinations are possible, we will consider all the combinations and choose the combination that yields the highest NPV and uses the entire facility to avoid under-utilization of resources.
Formula: NPV of a combined contract = sum of NPVs of individual contracts
Possible Combinations and their NPV at 100% use of facility:
Combination | Use of facility | Net Present Value |
Contract A | 100% | $5 million |
Contract B and C | 100% (50% + 50%) | $7 million ($3 million + $4 million) |
Therefore, I advice allocating 50% space to contract B and 50% space to contract C to yield an NPV of $7 million, which is higher than the NPV of $5 million if 100% space is allocated to Contract A.
Question 2)
a) Using the Gordon Growth Model of dividend discounting, we compute the stock price at the beginning of the fourth year. The formula of Gordon Growth Model is:
Price = Dividend in the year end / (Cost of equity capital - Perpetual Growth rate)
For Year 4, the dividend at year beginning is $3. The dividend at year end is:
Dividend at beginning of the year * (1+Growth rate) = $3 * (1+10%) = $3.30
Cost of equity capital is 15% and the perpetual growth rate is 10%.
Now, we use the stated formula to compute Price of the stock at the end of Year 4:
Price = $3.30 / (15%-10%) = $66
b) For calculating the current price, we will discount back all the future cash flows to the present at the cost of equity capital.
Formula for Present Value : Present Value = Cash Flow / (1+Interest Rate)^Time period
Year | Cash Flow | Formula | Present Value |
1 | $1 | $1 / (1+15%) | $0.892857143 |
2 | $2 | $2 / (1+15%)^2 | $1.512287335 |
3 | $3 + $66 = $69 | $69 / (1+15%)^3 | $45.36862004 |
Total Present Value | $47.75047259 |
Note: The value of Cash flow in the 3rd is the sum of the dividend of $3 received during that year and the price of the stock at that time (Beginning of Year 4 = End of Year 3).
Therefore, the current price of the stock is $47.75.
Dl CHaranda Final-May 16, 2019 Name and signature: Manolo Felician 0 1. You have 1.5 hours to complete the exam, or equivalently 45 minutes for each exam page. 2. You can only use your (financial...
avakis FN 305-Foundations of Finandal Management Soring 2019- Final Exam Student: Directions: Complete all answers on separate paper. Use pencil for all problems. Show the formula first and can check your answer with the financial calculator, but do not just write down a number you got from your calculator. The problems count 23 points each and the discusslon question counts 39 points for a total of 200 points. Use a pen to write the discussion question. (Assume 365 days per...
You and your team are financial consultants who have been hired by a large, publicly traded electronics firm, Brilliant Electronics (BE), a leader in its industry. The company is looking into manufacturing its new product, a machine using sophisticated state of the art technology developed by BE’s R&D team, overseas. This overseas project will last five years. They’ve asked you to evaluate this project and to make a recommendation about whether or not the company should pursue it. BE’s management...
HTML Create a webpage with three divisions. Division 1 occupies the left-side of the page with a few links of your choice. Division 2 and 3 have the same width. You may use % to specify the width. For example, for division 1: width:20%, and for division 2 and 3: width:80%. Division 2 is used to display an image of your choice using the background-image property. Division 3 is to show the double-declining depreciation table, and has a background color...
5) Prepare An Analysis Of Market Strength by calculating for each company the: a) price/earnings ratio b) dividend yield 6) Once you have completed the first 5 steps, write a 1-2 page analysis of the Buckle . What is the strengths, weaknesses, etc.? Why would you invest ot not? Information for #6 : 2) Prepare a Profitability And Total Asset Management Analysis by calculating for each company the: a) profit margin b) asset turnover c) return on assets A) Profit...
A thumbs Up will be Given: 1.Can you respond to question #5,8,9,10,11 they are written responses 2. Show work for the answers in Table 2 Also below assignment, is the answers for the first half to see the work Max was recently hired by Imagine Software Inc. as a junior budget analyst. He is working for the Venture Capital Division and has been given for capital budgeting projects to evaluate. He must give his analysis and recommendation to the capital...