YEAR 1 | YEAR 2 | YEAR 3 | YEAR 4 | |||||||||||||||
Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | |||
DEVELOPMENT COST [1400/3QUARTER] | -466.67 | -466.67 | -466.67 | |||||||||||||||
PILOT TESTING | -200 | -200 | ||||||||||||||||
RAMP UP COST | -400 | -400 | ||||||||||||||||
MARKETING AND SUPPORT COST [150000/4QTR] =37500 PER QUARTER | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | -37.5 | |||||
PRODUCTION VOLUME UNIT [60000/4QTR] | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | ||||||
UNIT PRODUCTION COST | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | ||||||
TOTAL PRODUCTION COST IN 000 DOLLARS | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | -1500 | ||||||
SALES UNIT | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | 15000 | ||||||
PRICE PER UNIT | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | ||||||
REVENUE[SALES UNIT *PRICE PER UNIT] IN 000 DOLLARS | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | 3300 | ||||||
CASH FLOWS | -466.67 | -466.67 | -1066.67 | -637.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | 1762.5 | ||
DISCOUNT FACTOR AT 8% [1/1.08]N | 1 | 1 | 1 | 1 | 0.9259 | 0.9259 | 0.9259 | 0.9259 | 0.85733 | 0.85733 | 0.85733 | 0.85733 | 0.7938 | 0.7938 | 0.7938 | 0.7938 | ||
PRESENT VALUE OF CASH FLOWS | -466.67 | -466.67 | -1066.67 | -637.5 | 1631.89 | 1631.89 | 1631.89 | 1631.89 | 1510.61 | 1510.61 | 1510.61 | 1510.61 | 1399.07 | 1399.07 | 1399.07 | 1399.07 | ||
NPV | 15529$ | |||||||||||||||||
[-2637.51+6527.56+6042.44+5596.28] | ||||||||||||||||||
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost $ 800,000 Estimated...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estinated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost $ 1,100,000 Estimated...
Problem 3-10 The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost $ 1,150,000...
Development cost $ 1,300,000 Estimated development time 9 months Pilot testing $ 200,000 Ramp-up cost $ 400,000 Marketing and support cost $ 150,000 per year Sales and production volume 60,000 per year Unit production cost $ 100 Unit price $ 210 Interest rate 8 % Assume all cash flows occur at the end of each period. a. What is the net present value (discounted at 8%) of this project? Consider all costs and expected revenues. (Enter your answer in thousands...
Based on the original sales level of 60,000, what is the effect on NPV caused by changing the discount rate to 9%, 10%, or 11%? (Enter your answer in thousands of dollars. Perform all calculations using Excel. Do not round any intermediate calculations. Round your answer to the nearest thousand.) Development cost $ 1,300,000 Estimated development time 9 months Pilot testing $ 200,000 Ramp-up cost $ 400,000 Marketing and support cost $ 150,000 per year Sales and production volume 60,000...
You are getting ready to start a new project that will incur some cleanup and shutdown costs when it is completed. The project costs $5.35 million up front and is expected to generate $1.16 million per year for 10 years and then have some shutdown costs at the end of year 11. Use the MIRR approach to find the maximum shutdown costs you could incur and still meet your cost of capital of 14.9% on this project. . (Round to...