The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project.
Development cost | $ | 800,000 | |
Estimated development time | 9 | months | |
Pilot testing | $ | 200,000 | |
Ramp-up cost | $ | 400,000 | |
Marketing and support cost | $ | 150,000 | per year |
Sales and production volume | 60,000 | per year | |
Unit production cost | $ | 100 | |
Unit price | $ | 160 | |
Interest rate | 8 | % | |
Tuff Wheels also has provided the project plan shown below. As can be seen in the project plan, the company thinks that the product life will be three years until a new product must be created.
Assume all cash flows occur at the end of each period.
a. What is the net present value (discounted at 8%) of this project? Consider all costs and expected revenues. (Enter your answer in thousands of dollars. Perform all calculations using Excel. Do not round any intermediate calculations. Round your answer to the nearest thousand.)
b. What is the impact on NPV for the Kiddy Dozer
if the actual sales are 50,000 per year? 70,000 per year?
(Enter your answer in thousands of dollars. Perform all
calculations using Excel. Do not round any intermediate
calculations. Round your answer to the nearest
thousand.)
c. Based on the original sales level of 60,000,
what is the effect on NPV caused by changing the discount rate to
9%, 10%, or 11%? (Enter your answer in thousands of
dollars. Perform all calculations using Excel. Do not round any
intermediate calculations. Round your answer to the nearest
thousand.)
Solution:
Model
(a)
NPV base case (in thousands on dollar) = $13,239
(b)
Change cell $C$2 in the model with 50 and 70
NPV50,000 = $10,661
NPV70,000 = $15,816
(c)
Change cell $K$20 in the model with 9%, 10%, and 11%. Keep cell $C$2=60
NPV9% = $12,971
NPV10% = $12,711
NPV11% = $12,458
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost $ 1,100,000 Estimated...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estinated development time...
The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost $ 1,150,000...
Problem 3-10 The Tuff Wheels was getting ready to start its development project for a new product to be added to their small motorized vehicle line for children. The new product is called the Kiddy Dozer. It will look like a miniature bulldozer, complete with caterpillar tracks and a blade. Tuff Wheels has forecasted the demand and the cost to develop and produce the new Kiddy Dozer. The table below contains the relevant information for this project. Development cost Estimated...
Development cost $ 1,300,000 Estimated development time 9 months Pilot testing $ 200,000 Ramp-up cost $ 400,000 Marketing and support cost $ 150,000 per year Sales and production volume 60,000 per year Unit production cost $ 100 Unit price $ 210 Interest rate 8 % Assume all cash flows occur at the end of each period. a. What is the net present value (discounted at 8%) of this project? Consider all costs and expected revenues. (Enter your answer in thousands...
Based on the original sales level of 60,000, what is the effect on NPV caused by changing the discount rate to 9%, 10%, or 11%? (Enter your answer in thousands of dollars. Perform all calculations using Excel. Do not round any intermediate calculations. Round your answer to the nearest thousand.) Development cost $ 1,300,000 Estimated development time 9 months Pilot testing $ 200,000 Ramp-up cost $ 400,000 Marketing and support cost $ 150,000 per year Sales and production volume 60,000...
Mark Price, the new productions manager for Speakers and Company, needs to find out which variable most affects the demand for their line of stereo speakers. He is uncertain whether the unit price of the product or the effects of increased marketing are the main drivers in sales and wants to use regression analysis to figure out which factor drives more demand for its particular market. Pertinent information was collected by an extensive marketing project that lasted over the past...