Question

A project was originally estimated to be completed at a cost of $325,000. The cost of what’s been completed so far is $2...

A project was originally estimated to be completed at a cost of $325,000. The cost of what’s been completed so far is $250,000, and the project team has completed roughly 12 of the 16‐ week completion estimate.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

250000/325000 = 77% of Budget at completion

The project has exhausted 71% of the total budget

12/16 = 75% of budgeted time

The project has completed 75% of the estimated time

earned value = 75% * 325000 = 243750

Cost variance = Earned value - actual cost = 243750- 2750000 = - $6250

The project is running behind budget and incurring more cost than projected/expected

Add a comment
Know the answer?
Add Answer to:
A project was originally estimated to be completed at a cost of $325,000. The cost of what’s been completed so far is $2...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project is scheduled to be completed within 16 months and the total cost of the...

    A project is scheduled to be completed within 16 months and the total cost of the project is 500,000 USD. Eight months have passed and 220,000 USD has been spent. After a closer review, you (as a project leader) found that only 40% of the work has been completed so far, while 50% work was expected. Complete the following? Find the following values: PV = _______                                                                     EV = _______ SPI= _______                                                                      CPI = _______

  • A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of t...

    A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget? c. How much additional money will be required to finish this project? d....

  • An equipment has been purchased for a project to be completed in 6 years. The initial...

    An equipment has been purchased for a project to be completed in 6 years. The initial cost of equipment was Rs. 7,500,000. It is estimated that the used equipment can be sold in auction at a price of Rs. 1,200,000 after completion of the project. The expected/planned yearly usage of the equipment is as follows: Equipment Usage (Hours) 140 170 Year 1 2 3 4 5 6 230 80 110 70 Develop the yearly depreciation schedule of the equipment according...

  • An equipment has been purchased for a project to be completed in 6 years. The initial...

    An equipment has been purchased for a project to be completed in 6 years. The initial cost of equipment (6) was Rs. 7,500,000. It is estimated that the used equipment can be sold in auction at a price of Rs. 1,200,000 after completion of the project. The expected/planned yearly usage of the equipment is as follows: Year Equipment Usage (Hours) 1 140 2 170 3 230 4 80 5 110 6 70 Develop the yearly depreciation schedule of the equipment...

  • Q.3 An equipment has been purchased for a project to be completed in 6 years. The...

    Q.3 An equipment has been purchased for a project to be completed in 6 years. The initial cost of equipment was Rs. 7,500,000. It is estimated that the used equipment can be sold in auction at a price of Rs. 1,200,000 after completion of the project. The expected/planned yearly usage of the equipment is as follows: Year Equipment Usage (Hours) 1 140 2 170 3 230 4 80 5 110 6 70 Develop the yearly depreciation schedule of the equipment...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • A project has 114 activities. At the end of period 4, it has been reported that...

    A project has 114 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с Total Budgeted Cost($) 20 15 100 D 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • A project has 117 activities. At the end of period 4, it has been reported that...

    A project has 117 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B С D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What ef...

    Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What effect would you expect this to have on the schedule? Select one: a. Task B would have 1 day of lag b. The project completion date would be increased by 3 days. c. Task B is now part of the critical path...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT