Scenario Operations managers use many techniques to solve problems. Some of these techniques are graphical and can be solvedTime (Min) Activity Description Immediate Predecessors Aircraft stops at the gate :05 Jet bridge connected Passengers deplaneExpand All Collapse All Step 1: Produce a Gantt Chart Use Excel to produce a Gantt chart of the aircraft servicing process frStep 2: Draw an AON Network Diagram Create a slide to construct a diagram of activity on node (AON) network of the aircraft

Scenario Operations managers use many techniques to solve problems. Some of these techniques are graphical and can be solved using software tools and programs. Before you start this activity, review the Excel for Operations Management Software page and download Microsoft Excel and the Excel for OM plugin. You will use these tools to solve real-life problems encountered by operations managers. How many times have you waited, not so patiently in the departure area, for your aircraft to be serviced before you board? Airport operations managers strive to achieve the shortest "turn around time" possible through a carefully choreographed process. Aircraft only make money when they are in the air! This chart provides a generalized flow for the turnaround of an aircraft. Your task is to produce a Gantt chart, draw an activity on node (AON) network diagram, and determine the critical path.
Time (Min) Activity Description Immediate Predecessors Aircraft stops at the gate :05 Jet bridge connected Passengers deplane Baggage offloaded Refueling/water servicing :25 Gallery servicing :25 Cabin cleaning :30 Baggage loaded E, F, G Passengers boarded Aircraft ready for departure Complete the steps in each section and then submit your assignment for grading
Expand All Collapse All Step 1: Produce a Gantt Chart Use Excel to produce a Gantt chart of the aircraft servicing process from the time the aircraft stops at the gate until it is ready for departure. Use this information to create your chart. Use the Gantt Chart project planner template to get started. In Excel, select New and then search for the planner. Assume that the PLAN START (earliest start time) begins as soon as the predecessor is completed. Set the ACTUAL START, ACTUAL DURATION, and PERCENT COMPLETE . time to O (since we are only using this chart for planning the project) Once you have completed your Gantt chart, study it and provide suggestions on ways to shorten the turn around time. Remember that some items must be completed before others can start (i.e., the jet bridge must be connected before you can offload the passengers and the aircraft cannot have passengers aboard when refueling)
Step 2: Draw an AON Network Diagram " Create a slide to construct a diagram of activity on node (AON) network of the aircraft turnaround operation. Step 3: Determine the Critical Path Use your AON network diagram to determine the critical path and calculate the total time of completion. Make sure to annotate the critical path and time of completion on the slide. Once you produce the AON graph consider what would happen if activity G cabin cleaning could be reduced to: 20 minutes. Write a brief statement on the changes to the critical path and time of completion. Place your statement on the slide. Step 4: Submit the Assignment Submit your Gantt chart and your network diagram slide. Save your assignment using a naming convention that includes your first and last name and the activity number (or description). Do not add punctuation or special characters. Review the Problems Rubric for detailed grading information.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The Gantt chart obtained is as follows-

23 52It can be clearly observed from the Gantt chart that the B,C, G & I are the activities limiting the turn around time. We shall also realize that activities B (Jet Bridge Connected), C (Passenger deplane) & I (Passenger Boarded) are some of the non-controllable activities and manipulating them would compromise the safety and customer satisfaction quotient of the process.

Therefore, we should specifically target reducing the time taken to clean the cabin, which requires the highest time in the process. We should implement process which should ensure reduction in cabin wastes. In addition to this, we can also put in more personnel to reduce the effort/person in this activity and thus reducing the required time further. nevertheless, we can also put in more personals in activities other than B,C, G & I, to reduce respective time durations.

The AON for the process along with its critical path (marked in Red) is as shown-

0 10 10 20 ES EF 15 40 0 5 15 40 0 0 45 55 5 15 15 45

The Critical path is A-B-C-G-I-J making the turn around time of 55

On reducing the activity time of G to 20, the network will look like this-

0 10 10 20 ES EF 15 40 0 50 50 15 40 0 0 40 50 5 15 15 35It can be seen that we now obtain two critical paths, A-B-C-F-I-J & A-B-C-E-I-J making the turn around time to a reduced value of 50.

Please Like & Provide your reviews in comments. :-)

Add a comment
Know the answer?
Add Answer to:
Scenario Operations managers use many techniques to solve problems. Some of these techniques are graphical and can be s...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT