Answer will be the 1.34.

BCR = Benefit / Cost

P = $2500 + ($300)(P/A, 10%, 12) +(1.40 hot) (600 hours X (P/A, 10%, 12) - ($300) (P/F, 10%, 12) = $2500+ ($300 + $840)(6.813

Add a comment
Know the answer?
Add Answer to:
10) An oil company is planning to install a new pipeline to connect storage tanks to a processing plant 1500 m away...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • show your work 10) An oil company is planning to install a new pipeline to connect storage tanks to a processing pla...

    show your work 10) An oil company is planning to install a new pipeline to connect storage tanks to a processing plant 1500 m away. A 120 mm pipe is being considered with the following characteristics. What is the benefit-cost ratio for this pipe using an annual interest rate of 10%? Initial cost $2500 Service Life 12 Years Salvage Value $300 Annual Maintenance $300 Pump Cost/Hour $1.40 Pump Operation 600 hours/year Estimated Benefits $2000/year a. 1.22 b. 1.34 c. 1.45...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT