Question

In a job-order costing system that is based on machine-hours, which of the following formulas is correct? A) Predeter...

In a job-order costing system that is based on machine-hours, which of the following formulas is correct?

A) Predetermined overhead rate = Actual manufacturing overhead ÷ Actual machine-hours

B) Predetermined overhead rate = Actual manufacturing overhead ÷ Estimated machine-hours

C) Predetermined overhead rate = Estimated manufacturing overhead ÷ Estimated machine-hours

D) Predetermined overhead rate = Estimated manufacturing overhead ÷ Actual machine-hours

41. Which of the following statements about using a plantwide overhead rate based on direct labor is correct?

A) Using a plantwide overhead rate based on direct labor-hours will ensure that direct labor costs are correctly traced to jobs.

B) Using a plantwide overhead rate based on direct labor costs will ensure that direct labor costs will be correctly traced to jobs.

C) It is often overly simplistic and incorrect to assume that direct labor-hours is a company's only manufacturing overhead cost driver.

D) The labor theory of value ensures that using a plantwide overhead rate based on direct labor will do a reasonably good job of assigning overhead costs to jobs.

42.   When preparing a direct materials budget, the required purchases of raw materials in units equals:

A) raw materials needed to meet the production schedule + desired ending inventory of raw materials − beginning inventory of raw materials.

B) raw materials needed to meet the production schedule − desired ending inventory of raw materials − beginning inventory of raw materials.

C) raw materials needed to meet the production schedule − desired ending inventory of raw materials + beginning inventory of raw materials.

D) raw materials needed to meet the production schedule + desired ending inventory of raw materials + beginning inventory of raw materials.

43.   All of Gaylord Corporation's sales are on account. Thirty-five percent of the sales on account are collected in the month of sale, 45% in the month following sale, and the remainder are collected in the second month following sale. The following are budgeted sales data for the company:

January

February

March

April

                 Total sales

$50,000

$60,000

$40,000

$30,000

What is the amount of cash that should be collected in March?

A) $24,000

B) $37,000

C) $41,000

D) $51,000

44.     Which of the following statements is NOT correct concerning the Manufacturing Overhead Budget?

A) The Manufacturing Overhead Budget provides a schedule of all costs of production other than direct materials and labor costs.

B) The Manufacturing Overhead Budget shows only the variable portion of manufacturing overhead.

C) The Manufacturing Overhead Budget shows the expected cash disbursements for manufacturing overhead.

D) The Manufacturing Overhead Budget is prepared after the Sales Budget.

45.     Assuming that direct labor is a variable cost, the primary difference between the absorption and variable costing is that:

A) variable costing treats only direct materials and direct labor as product cost while absorption costing treats direct materials, direct labor, and the variable portion of manufacturing overhead as product costs.

B) variable costing treats direct materials, direct labor, the variable portion of manufacturing overhead, and an allocated portion of fixed manufacturing overhead as

0 0
Add a comment Improve this question Transcribed image text
Answer #1

40. Predetermined overhead rate is computed by dividing Estimated manufacturing overhead by Estimated machine-hours.

(C) Predetermined overhead rate = Estimated manufacturing overhead ÷ Estimated machine-hours

41. (A) Using a plantwide overhead rate based on direct labor-hours will ensure that direct labor costs are correctly traced to jobs.

42. Closing stock = Opening Stock + Stock Purchases - Stock sent to Production

Therefore required purchases of raw materials in units = (A) raw materials needed to meet the production schedule + desired ending inventory of raw materials − beginning inventory of raw materials.

43. Cash to be collected in March = 35% of sales in March + 45% of sales in Feb + 20% of sales in Jan

= 35% ( 40,000) + 45% ( 60,000) + 20% (50,000)

= 51,000

44. Manufacturing overhead budget includes both variable portion and fixed portion. therefore false statement among the above is

(B) The Manufacturing Overhead Budget shows only the variable portion of manufacturing overhead.

Add a comment
Know the answer?
Add Answer to:
In a job-order costing system that is based on machine-hours, which of the following formulas is correct? A) Predeter...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: 30,300 Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour $575,700 4.00 16 Recently, Job T687 was completed 699 Number of units the job Total machine-hours Direct materials Direct labor cost $1, The amount of overhead applied to Job T687 is closest to NO Choice...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ $ 153,000 651,000 4.50 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 659,000 Variable manufacturing overhead cost per machine-hour $ 4.40 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The following information was...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ 156,000 658,000 4.30 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate Predetermined overhead per MH 2. During the year Job 500 was...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 $ 655,000 $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 156,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.80 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 153,000 s 654,088 $ 4.20 Required 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 159,000 Fixed manufacturing overhead cost $ 651,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $3.ee $650,0e0 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT