Question

NPV Project A Project X Cost of Capital 0% 30% 22% 12% What is the IRR of Project A?Use the information contained in the figure below, which contains the NPV profile for Project A (solid curved line) and for Project X (dashed curved line) to answer the following question.

What is the IRR of Project A?

a.

8%

b.

12%

c.

22%

d.

30%

e.

The IRR of Project A cannot be determined from this figure

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV is given by::

NPV = L Rt/(1 + i) ,t varies from 1 ton where Rt = Cash flow netted (Inflow - Outflow) during the period t i = Discount rat

FOR IRR,

The discount rate at which NPV = 0 is known as the IRR.

Hence, on the graph for Project A, we need to find the discount rate at which NPV - 0

The solid line (Project A) makes NPV = 0 at cost = 22% (x - axis)

Hence IRR = 22%(option C)

Add a comment
Know the answer?
Add Answer to:
Use the information contained in the figure below, which contains the NPV profile for Project A (solid curved line) and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • see the information contained in the figure below, which contains the NPV profile for Project A...

    see the information contained in the figure below, which contains the NPV profile for Project A (solid curved line) and for Project X (dashed curved line) to answer the following question. Choose the most accurate statement: If these projects are mutually exclusive, which project should be chosen by the CEO of the firm if the CEO’s primary objective is to maximize shareholder value. Assume the opportunity cost of capital is 10% for both projects. a. The CEO should select both...

  • Use the information contained in the figure below, which contains the NPV profile for Project A...

    Use the information contained in the figure below, which contains the NPV profile for Project A (solid curved line) and for Project X (dashed curved line) to answer questions 6 and 7. NPV Project A roject X Cost of Capital 0% 12% 22% 30% 6. Choose the most accurate statement. If these projects are mutually exclusive, which project should be chosen by the CEO of the firm if the CEO's primary objective is to maximize shareholder value. Assume the opportunity...

  • Which of the following statements is correct? (a) The NPV profile graph for a normal project...

    Which of the following statements is correct? (a) The NPV profile graph for a normal project will generally have a postive(upward) slope as the life of the project increase. (b) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life (c) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firms value varies with the cost of capital (d)...

  • Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at...

    Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown in the graph. Identify the range of costs of capital that a firm would use to accept and reject this project by responding to the drop-down choices below the graph. NPV (Dollars) A -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) B The point at which...

  • s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being...

    s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) Year Project W Project x 800 0 - $1,500 -$1,000 $200 $350 600 Project X 2 $350 $500 $400 $600 400 4 $600 $750 Project W 200...

  • HW help please with explanations Which project will you choose? Use the information to answer the...

    HW help please with explanations Which project will you choose? Use the information to answer the following questions. A company is analyzing two mutually exclusive projects, S and L, whose cash flows are shown below: Year o Year 1 Year 2 Year 3 Year 4 Cashflow for S -100 40 50 30 30 Cashflow for L -100 10 10 50 90 Assume the company can get an unlimited amount of capital at that cost. WACC NPV (S) NPV (L) 5%...

  • 1. Use the information in the table below to answer questions a-C. Project 4 5 NPV...

    1. Use the information in the table below to answer questions a-C. Project 4 5 NPV IRR 1496 Investment 1 $1,000,000 300,000 300,000 | 400,000 $1,450,000 500,000 500,000 500,000 $2,500,000 750,000 o 0 400,000 500,000 1,000,000 0 0 58.7 14.2% 3,000,000 507.9 a. If these projects listed above are independent, which ones would be accepted if you use a 3 year payback period? b. If the projects listed above are mutually exclusive, which one would be chosen using the NPV...

  • A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the...

    A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's Select (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the Select of the differences in the projects' cash flows (Project Delta). A Select NPV profile indicates that increases in the cost of capital...

  • 3 Problem Set: The NPV Rule 1 In Figure 1, the sloping straight line represents the opportunities for investment in the capital market, and the solid curved line represents the opportunities for...

    3 Problem Set: The NPV Rule 1 In Figure 1, the sloping straight line represents the opportunities for investment in the capital market, and the solid curved line represents the opportunities for investment in plant and machinery (real nassets). The company's only asset at present in $2.6 million in cash $ tomorrovw Owners prefenned consumption pastern 3.75 1 16 26 4 today Figure 1: This graph is used in problem #1 (a) What is the interest rate? (b) How much...

  • Refer to the graph of mutually exclusive projects shown above Kindly explain with reasoning the below...

    Refer to the graph of mutually exclusive projects shown above Kindly explain with reasoning the below a. At an 8% cost of capital, which project has a higher NPV? b. Where on the graph would there be a conflict between the NPV and IRR methods? In other words, under what conditions would the NPV method tell you that project B is better and the IRR method tell you that project A is better? c. What does the slope of these...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT