Question

5. On June 1, 2021, Coors Property Management entered into a 2-year contract to oversee leasing and maintenance for an a...

5. On June 1, 2021, Coors Property Management entered into a 2-year contract to oversee leasing and maintenance for an apartment building. The contract starts on July 1, 2021. Under the terms of the contract, Coors will be paid a fixed fee of $50,000 per year and will receive an additional 15% of the fixed fee at the end of each year provided that building occupancy exceeds 90%. Coors estimates a 30% chance it will exceed the occupancy threshold, and concludes that revenue recognition over time is appropriate for this contract. Assume Coors estimates variable consideration as the expected value. How much revenue should Coorsrecognize on this contract in 2021?

A) $25,000

B) $26,125

C) $28,750

D) $50,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

solutions Given data, fired fee & 50000 per year Received an additional isy of the fixed fee at the end of the year provided

Add a comment
Know the answer?
Add Answer to:
5. On June 1, 2021, Coors Property Management entered into a 2-year contract to oversee leasing and maintenance for an a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. On January 1, 2020, Jim Beam Company sold goods to a customer and received a...

    1. On January 1, 2020, Jim Beam Company sold goods to a customer and received a non interest bearing installment note requiring payments of $15,000 annually for six years. The first payment was received by Jim Beam Company on January 1, 2020. The prevailing rate of interest for this type of note is 8%.The total sales revenue Jim Beam Company would record for this sale on January 1, 2020 is : A)$90,000 B) $69,343 C) $74,891 D)$15,000 2. Johnnie Walker...

  • Emmet Property Management entered into a 2-year contract on June 1, 2016, to build an apartment...

    Emmet Property Management entered into a 2-year contract on June 1, 2016, to build an apartment building. The contract starts on July 1, 2016. Under the terms of the contract, Emmet will be paid a fixed fee of $1,500,000 and will receive an additional 10% of the fixed fee provided that building is ready to occupy at the end of the two years. Emmet estimates a 60% chance it will meet the completion date. The total costs of the project...

  • Emmet Property Management entered into a 2-year contract on June 1, 2016, to build an apartment...

    Emmet Property Management entered into a 2-year contract on June 1, 2016, to build an apartment building. The contract starts on July 1, 2016. Under the terms of the contract, Emmet will be paid a fixed fee of $1,500,000 and will receive an additional 10% of the fixed fee provided that building is ready to occupy at the end of the two years. Emmet estimates a 60% chance it will meet the completion date. The total costs of the project...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super...

    Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super Rise obtains a contract to maintain an elevator in a 90-story building in New York City for 10 months and receives a fixed payment of $80,000. The contract specifies that Super Rise will receive an additional $40,000 at the end of the 10 months if there is no unexpected delay, stoppage, or accident during the year. Super Rise estimates variable consideration to be the...

  • Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super...

    Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super Rise obtains a contract to maintain an elevator in a 90-story building in New York City for 10 months and receives a fixed payment of $98,000. The contract specifies that Super Rise will receive an additional $49,000 at the end of the 10 months if there is no unexpected delay, stoppage, or accident during the year. Super Rise estimates variable consideration to be the...

  • 6. Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super Rise obtains...

    6. Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2021, Super Rise obtains a contract to maintain an elevator in a 90-story building in New York City for 10 months and receives a fixed payment of $96,000. The contract specifies that Super Rise will receive an additional $48,000 at the end of the 10 months if there is no unexpected delay, stoppage, or accident during the year. Super Rise estimates variable consideration to be...

  • MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the...

    MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT