Solution 11:
Amount of employee salaries and wages included in planning budget = $57,000 + (35*$1,800) = $120,000
solution 12:
Amount of travel expense included in planning budget = 35*$950 = $33,250
Solution 13:
Amount of other expense included in planning budget = $36,000
Solution 14:
Activity variance of revenue = Budgeted revenue for actual activity - Budgeted revenue for budgeted activity
= (40*$5,800) - (35*$5,800) = $29,000 F
Solution 15:
Activity variance for expense = (Budgeted activity - Actual activity) * Variable amount per unit
Employee salaries and wages = (35-40) * 1800 = $9,000 U
Travel expense = (35 - 40) * $950 = $4,750 U
Other expense (35-40)* 0 = 0 None
Required information [The following information applies to the questions displayed below Adger Corporation is...
Required information [The following information applies to the questions displayed below] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Actual Element Variable Element Total for May per Month per Customer Served 6,000 1,700 Revenue 195,500 114,700 28,900 33,500 Employee salaries and wages Travel expenses 56,000...
Required information [The following information applies to the questions displayed below.) Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element Variable Element per per Customer Month Served $ 5,800 $ 57,000 $1,800 $ 950 $ 36,000 Revenue Employee salaries and wages Travel expenses Other expenses...
Required information [The following information applies to the questions displayed below Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element Variable Element Actual Total for May $ 217,000 $128,100 $35,300 $ 34,400 per Customer per Month Served Revenue $5,800 $1,800 Employee salaries and wages Travel...
! Required information [The following information applies to the questions displayed below.] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element Variable Element Actual per Customer Served Total per Month for May $ 189,500 $ 105,900 $ 25,600 $ 5,800 $ 1,500 Revenue Employee salaries...
Required information [The following information applies to the questions displayed below.] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element per Month Variable Element per Customer Served Actual Total for May Revenue $ 5,600 $ 182,000 Employee salaries and wages $ 55,000 $ 1,600 $...
Required information [The following information applies to the questions displayed below.] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element per Month Variable Element per Customer Served Actual Total for May Revenue $ 5,600 $ 182,000 Employee salaries and wages $ 55,000 $ 1,600 $...
Required information [The following information applies to the questions displayed below.] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element per Month Variable Element per Customer Served Actual Total for May Revenue $ 5,600 $ 182,000 Employee salaries and wages $ 55,000 $ 1,600 $...
Required information (The following information applies to the questions displayed below.) Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element Variable Element per per Customer Month Served $ 5,800 $ 54,000 $ 1,500 $ 800 $ 33,000 Revenue Employee salaries and wages Travel expenses Other...
The Foundational 15 [LO9-1, LO9-2, LO9-3) The following information applies to the questions displayed below Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below Element Variable Element Actual per Customer per Total Revenue Employee salaries and wages $ 6,300 $ 1,700 $ 620 199,000 s 127,300 $...
Required information [The following information applies to the questions displayed below.] Adger Corporation is a service company that measures its output based on the number of customers served. The company provided the following fixed and variable cost estimates that it uses for budgeting purposes and the actual results for May as shown below: Fixed Element per Month Variable Element per Customer Served Actual Total for May Revenue $ 5,600 $ 182,000 Employee salaries and wages $ 55,000 $ 1,600 $...