The payback method is most appropriate for projects whose cash flows do not extend far into the future.
true or False
Solution: Given statement in the question is True
Reason:
1) Payback period is the length of time required for the cumulative total net cash flows from investment to equal the total initial cash outflow.
2) Length of payback period serve as an estimate of project's risk. Longer the payback period, riskier the project as long term predictions are less reliable. Hence payback method is most appropriate for projects whose cash flows do not extend far into the future.
The payback method is most appropriate for projects whose cash flows do not extend far into...
Which of the statements below are true for the payback method of evaluating projects? ' The payback method ignores the time value of money. O The payback method considers all of the project cash flows. O The payback method uses an arbitrary all of the above. Two of the above.
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 3 4 1,250 3,500 - 6,000 - 2,000 - 6,000 1,250 2,000 1,250 +3,500 5,500 2,500 1,250 3,500 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a cutoff period of 3 years, which projects will you accept? d-1....
Here are the expected cash flows for three projects: Project Year: 4 0 - 5,100 - 1,100 - 5,100 Cash Flows (dollars) 2 3 + 1,025 + 1,025 + 3,050 0 + 1,100 + 2,050 + 1,025 + 1,025 + 3,050 + 3,050 + 5,050 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...
Here are the expected cash flows for three projects: Project Year: IU 0 - 5,700 - 1,700 - 5,700 Cash Flows (dollars) 1 2 3 + 1,175 + 1,175 + 3,350 0 + 1,700 + 2,350 + 1,175 + 1,175 + 3,350 4 0 + 3,350 + 5,350 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If...
Here are the expected cash flows for three projects: Project Year: 2 0 - 5,300 - 1,300 - 5,300 Cash Flows (dollars) 1 + 1,075 + 1,075 + 3,150 0 + 1,300 + 2,150 + 1,075 + 1,075 + 3,150 0 + 3,150 + 5,150 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...
Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 1 2 4 -5,300 -1,300 -5,300 +1,075 +1,075 +1,300 +1,075 +3,150 +2,150 +3,150 0 +3,150 +5,150 +1,075 a. What is the payback period on each of the projects? Project Payback Period years A В years C years AB C b. If you use a cutoff period of 2 years, which projects would you accept? O Project A O Project B O Project C O Project A...
Your firm is considering two projects with the following cash flows: Cash flows from project B (£000) (500) 200 250 170 25 30 Year Cash flows from project A (£000) 0(500) 167 180 160 100 100 4 1. Calculate the ARR and payback rule 2. If the appropriate discount rate is 12%, rank the two projects 3. Which project is preferred if you rank by IRR? 4. Calculate the discount rate (r) for which the NPVs of both projects are...
Question 20 1 pts Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost. WACC: 9.50% -$950 $500...
29. Payback and NPV. Here are the expected cash flows for three projects: (108-4) Pipject Year: 4 0 -5,000 - 1.000 -5.000 Cash Flows (dollars) 1 2 3 +1,000 +1,000 +3,000 0 +1,000 +2.000 +1,000 +1,000 +3,000 +3,000 +5.000 a. What is the payback period on each of the projects? b. Given that you wish to use the payback rule with a cutoff period of 2 years, which projects would you accept?
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...