Question

The standard labor cost in the production of a pair of Tri Town Brand athletic shoes is 0.40 hours at $14.00 per hour. During

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Labor rate variance = (Standard rate - actual rate) x Actual hours used
= ($14 - $100440/ 8370) x 8370 = $16,740 Favorable

Labor efficiency variance = (Standard hours - actual hours) x Standard rate

= (23370*0.40 - 8370)*14 = $13,692 Favorable

Add a comment
Know the answer?
Add Answer to:
The standard labor cost in the production of a pair of Tri Town Brand athletic shoes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The standard labor cost in the production of a pair of Beca Brand athletic shoes is...

    The standard labor cost in the production of a pair of Beca Brand athletic shoes is 0.40 hours at $14.00 per hour. During the month of June, 24,630 pairs were produced. Actual labor costs were $96,240 for 8,020 hours. Compute the labor rate and labor efficiency variances for the month of June. (Round actual wage rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.) Labor Rate...

  • Exercise 11-8 The standard labor cost in the production of a pair of Roger Brand athletic...

    Exercise 11-8 The standard labor cost in the production of a pair of Roger Brand athletic shoes is 0.40 hours at $12.00 per hour. During the month of June, 23,780 pairs were produced. Actual labor costs were $128,700 for 8,580 hours. Compute the labor rate and labor efficiency variances for the month of June. (Round actual wage rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 125. Enter all variances as a positive number.)...

  • At Happy Air, the standard quantity of labor is 22 hours per refrigeration unit. The standard...

    At Happy Air, the standard quantity of labor is 22 hours per refrigeration unit. The standard wage rate is $35. In July, the company produced 77 refrigeration units and incurred 2,100 labor hours at a cost of $71,400. Calculate the labor rate variance and the labor efficiency variance. Indicate whether the variances are favorable or unfavorable. (Round intermediate calculations to 2 decimal places, e.g. 14.37 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive...

  • Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs...

    Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $12.40) Direct labor (1.20 hours x $14.30) $11.16 $17.16 During May, the company produced 3,600 band hats; 3,910 yards of material were purchased for $44,574, and 3,120 yards of material were used in production. Also during May, 4,720 direct labor hours were worked at a cost of $61,360. Calculate material price...

  • Richetti Band Uniforms uses a standard costing system. The standard material and labor costs for producing...

    Richetti Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards × $11.70) $10.53 Direct labor (1.20 hours × $13.30) $15.96 During May, the company produced 3,770 band hats; 4,400 yards of material were purchased for $42,240, and 3,270 yards of material were used in production. Also during May, 4,790 direct labor hours were worked at a cost of $57,480. Calculate material price and quantity...

  • Lawn Band Uniforms uses a standard costing system. The standard material and labor costs for producing...

    Lawn Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards × $12.20) $10.98 Direct labor (1.20 hours × $13.70) $16.44 During May, the company produced 3,290 band hats; 4,340 yards of material were purchased for $44,702, and 3,300 yards of material were used in production. Also during May, 4,710 direct labor hours were worked at a cost of $61,230. Calculate material price and quantity...

  • Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs...

    Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.40) Direct labor (1.20 hours x $13.80) $10.26 $16.56 During May, the company produced 3,340 band hats; 3,870 yards of material were purchased for $41,022, and 3,050 yards of material were used in production. Also during May, 4,240 direct labor hours were worked at a cost of $59,360. Calculate material price...

  • Cinrich Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching ba...

    Cinrich Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.50) Direct labor (1.20 hours x $13.20) $10.35 $15.84 During May, the company produced 3,520 band hats; 3,770 yards of material were purchased for $36,946, and 2,900 yards of material were used in production. Also during May, 4,300 direct labor hours were worked at a cost of $60,200. Calculate material price and quantity...

  • Metlock Services, Inc. is trying to establish the standard labor cost of a typical brake repair....

    Metlock Services, Inc. is trying to establish the standard labor cost of a typical brake repair. The following data have been collected from time and motion studies conducted over the past month. Actual time spent on the brake repairs 3 hours Hourly wage rate $13 Payroll taxes 10% of wage rate Setup and downtime 12% of actual labor time Cleanup and rest periods 28% of actual labor time Fringe benefits 20% of wage rate Determine the standard direct labor hours...

  • Question 25 Nifty Nail Salon Limited is trying to determine the standard labour cost of a...

    Question 25 Nifty Nail Salon Limited is trying to determine the standard labour cost of a manicure. The following data has been collected after analyzing one month's work: actual time spent on a manicure 1 hour; hourly wage rate $11; payroll taxes 5% of wage rate; set-up and downtime 5% of actual labour time; cleanup and rest periods 12% of actual labour time. Determine the standard direct labour hours per manicure. (Round answer to 2 decimal places, e.g. 15.25.) Standard...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT