Labor rate variance = (Standard rate - actual rate) x Actual
hours used
= ($14 - $100440/ 8370) x 8370 = $16,740 Favorable
Labor efficiency variance = (Standard hours - actual hours) x Standard rate
= (23370*0.40 - 8370)*14 = $13,692 Favorable
The standard labor cost in the production of a pair of Tri Town Brand athletic shoes...
The standard labor cost in the production of a pair of Beca
Brand athletic shoes is 0.40 hours at $14.00 per hour. During the
month of June, 24,630 pairs were produced. Actual labor costs were
$96,240 for 8,020 hours. Compute the labor rate and labor
efficiency variances for the month of June. (Round
actual wage rate to 2 decimal places, e.g. 15.25 and final answers
to 0 decimal places, e.g. 125. Enter all variances as a positive
number.)
Labor Rate...
Exercise 11-8 The standard labor cost in the production of a pair of Roger Brand athletic shoes is 0.40 hours at $12.00 per hour. During the month of June, 23,780 pairs were produced. Actual labor costs were $128,700 for 8,580 hours. Compute the labor rate and labor efficiency variances for the month of June. (Round actual wage rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 125. Enter all variances as a positive number.)...
At Happy Air, the standard quantity of labor is 22 hours per
refrigeration unit. The standard wage rate is $35. In July, the
company produced 77 refrigeration units and incurred 2,100 labor
hours at a cost of $71,400.
Calculate the labor rate variance and the labor efficiency
variance. Indicate whether the variances are favorable or
unfavorable. (Round intermediate calculations to 2
decimal places, e.g. 14.37 and final answers to 0 decimal places,
e.g. 125. Enter all variances as a positive...
Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $12.40) Direct labor (1.20 hours x $14.30) $11.16 $17.16 During May, the company produced 3,600 band hats; 3,910 yards of material were purchased for $44,574, and 3,120 yards of material were used in production. Also during May, 4,720 direct labor hours were worked at a cost of $61,360. Calculate material price...
Richetti Band Uniforms uses a standard costing system. The
standard material and labor costs for producing a marching band hat
are as follows:
Materials (0.90 yards × $11.70)
$10.53
Direct labor (1.20 hours × $13.30)
$15.96
During May, the company produced 3,770 band hats; 4,400 yards of
material were purchased for $42,240, and 3,270 yards of material
were used in production. Also during May, 4,790 direct labor hours
were worked at a cost of $57,480. Calculate material price and
quantity...
Lawn Band Uniforms uses a standard costing system. The standard
material and labor costs for producing a marching band hat are as
follows:
Materials (0.90 yards ×
$12.20)
$10.98
Direct labor (1.20 hours ×
$13.70)
$16.44
During May, the company produced 3,290 band hats; 4,340 yards of
material were purchased for $44,702, and 3,300 yards of material
were used in production. Also during May, 4,710 direct labor hours
were worked at a cost of $61,230. Calculate material price and
quantity...
Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.40) Direct labor (1.20 hours x $13.80) $10.26 $16.56 During May, the company produced 3,340 band hats; 3,870 yards of material were purchased for $41,022, and 3,050 yards of material were used in production. Also during May, 4,240 direct labor hours were worked at a cost of $59,360. Calculate material price...
Cinrich Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.50) Direct labor (1.20 hours x $13.20) $10.35 $15.84 During May, the company produced 3,520 band hats; 3,770 yards of material were purchased for $36,946, and 2,900 yards of material were used in production. Also during May, 4,300 direct labor hours were worked at a cost of $60,200. Calculate material price and quantity...
Metlock Services, Inc. is trying to establish the standard
labor cost of a typical brake repair. The following data have been
collected from time and motion studies conducted over the past
month.
Actual time spent on the brake repairs
3 hours
Hourly wage rate
$13
Payroll taxes
10% of wage rate
Setup and downtime
12% of actual labor time
Cleanup and rest periods
28% of actual labor time
Fringe benefits
20% of wage rate
Determine the standard direct labor hours...
Question 25 Nifty Nail Salon Limited is trying to determine the standard labour cost of a manicure. The following data has been collected after analyzing one month's work: actual time spent on a manicure 1 hour; hourly wage rate $11; payroll taxes 5% of wage rate; set-up and downtime 5% of actual labour time; cleanup and rest periods 12% of actual labour time. Determine the standard direct labour hours per manicure. (Round answer to 2 decimal places, e.g. 15.25.) Standard...